Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : May - 2021,

Showing Page Number : 8 of 69

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
175
(OG)
160614-Restoration of flood damages / strengthening protection of District Head Quarter Offices, Buner SH: District Secretariat Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 72.341 64.23 8.111 0 0 0 64.23 0 100% 89%
May - 2021
2nd Revised PC-I amounting to Rs: 615.56 M based on designed by NUST on 08-12-20 Cannot be completed due to revision
No Image
District Secretariat PK-79 Buner
 
Scope of work:
  • Retaining wall
  • Add: work
 
176
(OG)
190457-Construction of Tehsil Administration complex at Matta Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 250 40 50 157.5 157.5 41.081 81.081 160 36% 32%
May - 2021
Tehsilder office - Super structure in progress. Main Building- foundation in progress.
No Image
Tehsil Administration  complex at Matta Swat.
177
(OG)
170642-Establishment of District Secretariat for Lower Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 349.501 88.764 18 13.5 13.5 4.272 93.036 242.737 31% 27%
May - 2021
Boundary wall in progress.
No Image
Lower Kohistan.
178
(OG)
150484-Construction of Deputy Commissioner Office cum Residence Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 104.382 72.351 10 7.5 7.5 4.862 77.213 22.031 79% 74%
May - 2021
01- Unit GF - roof laid, plastering in progress. FF - roofiing in progress. Mosque roof level, Residendial site not handed over
No Image
Battagram
 
Scope of work:
  • Main Building
  • Basement, G/F and F/F
  • Residence
  • G/F
  • Masjid
  • B/Wall
  • PCC Pavement
  • Foot Path
  • Sewerage Pipeline
  • Septic Tank (02 Nos)
  • Open Drains
  • Over Head Water Reservior
  • External Water Supply
  • External Electrificaiton
179
(OG)
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra
Mansehra
30-11--1 30-11--1 - 30-11--1 - 228.246 8.56 10 26.125 26.125 25.999 34.559 209.686 8% 15%
May - 2021
02- Units 1. Tehsil Building Development Work Completed, Main Building = Roofing in Progress. Boundary Wall in Progress. 2 DC Office Not yet started
No Image
Scope of work:
  • Tehsil Building (Double Story)
  • DC Main Office (Double Story)
  • Masjid
  • B/Wall
  • Parking
  • Internal Road
  • Foot Path
180
(OG)
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 194.728 194.665 0 0 0 0 194.665 0.063 - 100%
May - 2021
01-Unit Completed & H/O
No Image
Domel, District Bannu PK-87
 
Scope of work:
  • Main Building
  • Residentail Building
Category III Res: 01 No
Type IV Quarter: 02 Nos
Type V Quarter: 04 Nos
  • Masjid
  • Cafeteria
  • Compound Wall
  • Tube Well/O.H.T
180
(OG)
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu.
Mardan
30-11--1 30-11--1 - 30-11--1 - 206.858 206.421 0 0 0 0 206.421 0.437 - 100%
May - 2021
01- Unit Completed & H/O.
No Image
Katlang, Mardan
180
(OG)
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu.
Provincial
30-11--1 30-11--1 - 30-11--1 - 622.966 612.966 10 10 0 0 612.966 0 - -
May - 2021
Bannu + Mardan: Completed Swabi: Main building FF
No Image
180
(OG)
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu.
Swabi
30-11--1 30-11--1 - 30-11--1 - 221.38 196.772 0 0 0 0 196.772 24.608 - 89%
May - 2021
i. completed and H/Over ii. Boundary wall Completed. iii. Judicial Lock-up Finishing in progress iv. Cafeteria = Finishing in progress. v. Court Building = Finishing in progress. vi. Litigant Shed= Finishing in progress. vii. Residences Cat II PC-IV submitted. Quarters (6 NO.1) = PC-IV Submitted. viii. Mosque = Completed PC-IV submitted. ix. Over Head Tank = Completed. x. Outside Drain:- 90% Completed. xi. Internal Road = base course completed.
No Image
Tehsil building Rajjar Swabi PK-47
 
Scope of work:
  • Tehsil Building 
  • Judicial Lock-up 
  • Residences (06 Quarters & One Banglaw) 
  • B/Wall 
  • Dev: work 
181
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla
Nowshera
30-11--1 30-11--1 - 30-11--1 - 292.063 56.974 0 0 0 0 56.974 235.089 - 20%
May - 2021
PC-II; 5.00 dated: 04-09-14 01-Unit Work order issued, site not handed over by client departement due to court stay
No Image
Sub Divisional Complex at Jehangira Nowshera<
181
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla
Provincial
30-11--1 30-11--1 - 30-11--1 - 200 159.562 10 10 0 0 159.562 0 - -
May - 2021
No Image
181
(OG)
140977-F/S, Design & Construction of Sub-Divisional Complex at Jehangira, Nowshera and Besham, Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 99.805 97.85 0 0 0 0 97.85 1.955 - 98%
May - 2021
01- Unit Completed
No Image
Sub Divisional Complex at Besham Shangla
 
Scope of work:
  • Main Building
  • Dev: work
  • B/Wall
  • Cat-III Residence
  • Int:/Ext: Elect: & W/S
182
(OG)
160499-Provision for Rehabilitation of Disaster Affected Government Buildings
Kohistan
30-11--1 30-11--1 - 30-11--1 - 42.475 17.641 0 0 0 0 17.641 24.834 - 42%
May - 2021
Plaster progress. Roofing in progress.
No Image
Construction of the Sereatriat Tehsil Building
182
(OG)
160499-Provision for Rehabilitation of Disaster Affected Government Buildings
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 30.346 0 0 0 0 0 0 30.346 - -
May - 2021
NOC from Admin Deptt awaited for demolishing of ol
No Image
Re-construction of Mosque
182
(OG)
160499-Provision for Rehabilitation of Disaster Affected Government Buildings
Provincial
30-11--1 30-11--1 - 30-11--1 - 72.821 20.705 20.609 20.609 0 0 20.705 0 - -
May - 2021
Kohitan: Work started. Redesigning of foundation /
No Image
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
May - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Scope of work:
  • Main Building
  • B/Wall
  • Tube Well
  • Sub Offices
  • Chowkidar/Gurads Room
  • Water supply
  • Elec: Work
  • External Elec:
  • Over Head Tank 10000 Gallon
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
May - 2021
Rs: 20 M approved for Land acquisation Section -IV issued
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 2.5 2.5 2.5 2.5 38 52.446 42% 42%
May - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Provincial
30-11--1 30-11--1 - 30-11--1 - 330.348 35.5 15 15 0 0 35.5 0 - -
May - 2021
No Image
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
PS
30-11--1 30-11--1 - 30-11--1 - 0 5.005 0 0 0 0 5.005 0 - -
May - 2021
No Image
184
(OG)
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 290.832 0 0 0 0 0 0 290.832 - -
May - 2021
01-Unit Work order issued to contractor. Site not identified and not handed over
No Image
Constn of Tehsil Building at Gumbat District Kohat PK-80
  • Main Building
  • E/Wall
  • Ext: W/Supply
  • Bore Hole
  • O.H.T
  • Mosque
184
(OG)
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa
Mardan
30-11--1 30-11--1 - 30-11--1 - 640.887 0 0 0 0 0 0 640.887 - -
May - 2021
03- Units . 1 Site not yet cleared 2 Tender under process 3 Site not yet cleared
No Image
1) Constn: of Sub Divisional offices at Tehsil complex Takhtbai U/C Ganjai Maredan Pk-54.
2) Constn: of Tehsil Building for newly created Tehsil Rustam Pk-49
3) Constn: of Tehsil Building for newly created Tehsil U/C Gari Kapura Pk-51
184
(OG)
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 - 1070.813 0 20 20 0 0 0 0 - -
May - 2021
No Image
185
(New)
200255-Construction of District Headquarter of District Upper Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 15 0 10 0 0 0 0 5 67% -
May - 2021
Techincal bids re-submiited on 20-05-21
No Image
186
(New)
200322-F/S of District Secretariat, Palas Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 Line Deptt 3 0 0 0 0 0 0 0 - -
May - 2021
PC-II submitted for Rs.10.00 (M). RFP called. DCSC Awaited.
No Image
187
(OG)
191114-170306-M&R / Rehabilitation of Existing Buildings & Construction of APO/APA Compound in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 77.977 61.2981 47.977 16.686 16.686 3.155 64.4531 0 100% 83%
May - 2021
08- Units 04- Completed 04- In finishing stage.
No Image
Package A
Package B
Package C
Package D
Package E
Package F
Package G
Package H
 
188
(OG)
191155-180099 - Construction / Improvement & Rehabilitation of Tehsil Offices & Construction of Rest House in District South Waziristan. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 40.236 17.658 15 12.92 12.92 6.181 23.839 7.578 81% 59%
May - 2021
03- Units 1- Completed & H/O 2- Compount wall in progress. 3- M. Buld: upto roof level
No Image
1 Rest House at Haji Sharif Khan Kot Birmal
2 Rest House at Dr. Hakeem Khan Ghozi Khel Kalai Shakkai
3 Const: of The: Building Shawal
 
Scope of work:
Maing Building
C/Wall
 
189
(OG)
191167-180503 - Rehabilitation of Tribal District Administration Buildings and residences and provision of missing facilities in District South Waziristan. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 34.265 15.719 14.265 14.265 14.265 4.024 19.743 4.281 88% 58%
May - 2021
06- Units 1. Finishing stage 2. Roof level 3. Completed & H/O 4. Completed & 5. Completed & H/O 6. Roof Laid, Plastering in progress
No Image
1 A.C Sarwekai
2 AC Ladha Office
3 Ministerial Staff Qaurter i/c Class IV Servants Quarter in D.C S.W
4 1st Floor of Main Office Builidng at Tank
5 Add: Room at Add: Deputy Commissioner S.W
6 Rehab: Exisitng Quarter In D.C S.W Wana
190
(OG)
191170-160050-Rehabilitation, Improvement & Additional Works in SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 59.72 59.548 5 5 5 0 59.548 0 100% 100%
May - 2021
13- Units 1. Completed & H/O 2. Completed & H/O 3. Completed & H/O 4. Complete 5. Completed & H/O 6. Completed 7. Completed 8. Completed 9. Completed 10. Completed 11. Completed 12. Completed 13. Complete
No Image
1 Wana Sub DIvision
2 Jandola/Ladha Sub Divison
3 Furnihsing Items
 
Scope of work:
  • Group Toilet
  • C/Wall
  • Gate watch Tower
  • Drain
  • Sum Room
  • Breast/R/Wall
  • Fiber Glass
  • Railing etc
191
(OG)
191127-160174-Repair, Rehabilitation & Provision of Missing Facilities in Government Residential Buildings in NWA. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 115.064 89.464 23.827 12 12 10.069 99.533 1.773 98% 87%
May - 2021
09- components. 06- completed. 03- in progress.
No Image
Miran shah Tehsil
1 16 Nos Type II Reisdence
2 14 Nos Type III Reisdence and 37 Nos Qatrs
3 49 Nos Qatrs and 13 No OHT ETC
Mir Ali/Ramzak Tehsil
1 Dosali
2 Garyum
3 Razmak
4 Shewa
5 Spinwam
6 Mirali
201
(OG)
191163-180499 - Rehabilitation of Districts Administration Buildings and residences and provision of missing facilities in District Khyber. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 68.749 45.281 14.816 10.477 10.477 5.421 50.702 8.652 87% 74%
May - 2021
02 Units 1 work in progress 2 Near Completion
No Image
1 Repair/Rehab: of Government Residences at Dogra Bara
2 Office of XEN Building Khyber
202
(OG)
191128-170048-Construction of security wall and fencing around Civil Colony Ekkaghund. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 19.952 17.952 2 2 2 2 19.952 0 100% 100%
May - 2021
01- Unit Completed
No Image
Construction of security wall and fencing around Civil Colony Ekkaghund. [MA]
203
(OG)
191162-180498 - Rehabilitation of Districts Administration Buildings and residences and provision of missing facilities in District Mohmand. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 50 5.5 46 25.796 25.796 25.796 31.296 0 100% 63%
May - 2021
01- Unit Finishing
No Image
missing facilities in District Mohmand. [MA]
 
Scope of work:
  • Expansion of Rest House
  • Office at DC Region
  • Add: DC Region
  • DC House
  • Dev: work
204
(OG)
191146-180205 - Construction of Bachelor Suits in Civil Colony Khar District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 56.928 34.696 56.928 28.361 28.361 11.026 45.722 0 100% 80%
May - 2021
04- Units 1. H/O 2. H/O 3. Finishing 4. Finishing
No Image
1 Bachelor Suits for officials
2 Bachelor Suits for officer
3 Bachelor Hostel 1
4 Bachelor Hostel 2
 
Scope of work:
  • Official Suits
  • Officers Suits
  • Bachelor Hostel No 1
  • Bachelor Hostel No 2
 
205
(OG)
191148-180208 - Construction of Office Building for District Administration in Civil Colony Khar District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 30.099 13.099 14.901 10.497 10.497 7.903 21.002 2.099 93% 70%
May - 2021
01- Unit Finishing
No Image
Office Building for District Administration in Civil Colony Khar District Bajaur.
206
(OG)
191161-180497 - Rehabilitation of Districts Administration Buildings and residences and provision of missing facilities in District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 33.135 31.7 5 5 5 5 36.7 0 100% 100%
May - 2021
02- Units 1- Completed 2- Completed
No Image
1 Conference Room & DC House
2 Reh: of  Existing Builidng
 
207
(OG)
191174-160474-Acquisition of Land for Administrative Complex at Shah Kas Jamrud, Khyber Agency. (Phase-I). (Reg.Dev) [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
The scheme is approved for 400 M. Further evaluation of land will be carried out by the District Administration.
No Image
Land for Administrative Complex at Shah Kas Jamrud, Khyber Agency
207
(OG)
191174-160474-Acquisition of Land for Administrative Complex at Shah Kas Jamrud, Khyber Agency. (Phase-I). (Reg.Dev) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 11.267 11.267 0 0 0 0 - -
May - 2021
No Image
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 36.516 0 0 0 0 0 0 0 -
May - 2021
02- Units 1 Completed upto lintel level 2 Foundation in progress
No Image
1 Division Office Bittani Wazir at Bannu
2 Residentail Accomodation for SE (S) & Divisional Office Wazir Bittani
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 7.332 2.492 0 0 0 0 2.492 4.84 - 34%
May - 2021
04- Units 1 to 3 in progress & S.No.4 completed.
No Image
1 A.C Darzinda House
2 C&W Rest House near Aman Mela Check Post
3 Adminstraton Rest House Khoi Bahara
4 SDO C&W HOuse
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 52.125 29.725 1 1 1 1 30.725 21.4 59% 59%
May - 2021
2- Unit - Finishing stage
No Image
1 Const: of 4th Floor in C&W Circle Peshawar
2 Reh: of Office/Residences at Sub Division Landi Kotal
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 16.509 2.606 28.796 1 1 1 3.606 0 100% 22%
May - 2021
01- Unit Roof laid.
No Image
Const: of Bachlor Suit at Civil Colony Ghallanai
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 32.394 5.314 2.278 2.278 2.278 2.278 7.592 24.802 23% 23%
May - 2021
2- Units, 01 upto DPC level, and 2nd work in progress. 1- in Progress. 2- completed 3- Finishing in progress.
No Image
1 Const: of C&W Staff Hostel
2 Reh: of Residences
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 227.451 45.54 20.362 20.362 0 0 45.54 0 - -
May - 2021
No Image
208
(OG)
191175-180048 - Construction / Rehabilitation of Office / Residential Accommodation for FATA Employees in Tribal Districts. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 25.428 2.031 4 4 4 2.854 4.885 19.397 24% 19%
May - 2021
01- Unit Upto roof level
No Image
Const: of office/Residental Accodmation for Builidng/Highway Officials at Ladha
209
(OG)
191116-170250-Strengthening of Political Compound at Jandola in FR Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 12 6.472 1.84 1.84 1.84 1.84 8.312 3.688 69% 69%
May - 2021
MB Roof level. C/W 75% completed. Quarter layout given.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 11.694 11.694 0 0 0 100% -
May - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
211
(OG)
191143-180300 - Renovation / Reconstruction of DC/PA Compound in Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 19.998 16.352 5.146 3 3 3 19.352 0 100% 97%
May - 2021
Flooring completed. C/Wall in progress.
No Image
212
(OG)
191158-180513 - Construction of Residential Annexy D.C/PA House in Sub-Division DI Khan [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 30.734 10 23.734 17 17 12 22 0 100% 72%
May - 2021
Main building upto roof level. C/Wall in progress.
No Image
F.R D.I Khan
213
(OG)
191159-180514 - Construction of Various Departments / offices at Distt Compound Darazinda in Sub-Division DI Khan. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 32.832 9.437 23.395 15 15 13.006 22.443 0 100% 68%
May - 2021
Compount wall 70% completed. Approach road & Tube well in progress.
No Image
F.R D.I Khan
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69