Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : May - 2021,

Showing Page Number : 56 of 69

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Buner
HW
30-11--1 30-11--1 - 30-11--1 - 209.5 14.937 81.072 81.072 81.072 51.308 66.245 113.491 46% 32%
May - 2021
Work in progress. Revised Dce submiotted to SOR
No Image
1. Construction /Improvement/Widening of Road from Char to Elum (PK-20) District Buner
2.
i. Construction , Improvement , Up-gradation, Strengthening and Blacktopping of Tera to Pyaz road 02-KM PK-21
ii. Construction , Improvement , Up-gradation, Strengthening and Blacktopping of Parshalay Road 1.70-KM PK-21
iii. Construction , Improvement , Up-gradation, Strengthening and Blacktopping of Ladwan to Dagrai road 01-KM PK-21
 
 
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 35.521 25.8 4.53 4.53 4.53 1.57 27.37 5.191 85% 77%
May - 2021
bridge work completed, work on approach road under progress.
No Image
RCC bridge Mori PK-89
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 30 0 1 1 1 1 1 29 3% 3%
May - 2021
Length 2.5 km - Physically completed. Liability 7 M
No Image
Construction of Various Road in Pk-96 D.I Kha
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 140 24 4.5 4.5 4.5 4.5 28.5 111.5 20% 20%
May - 2021
10 Units Work in progress. Demand Rs. 10 M
No Image
Construction of road from Rehanpur to Bypass road
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 17.876 0 0 0 0 0 0 17.876 - -
May - 2021
Site Dipsute
No Image
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Haripur
HW
30-11--1 30-11--1 - 30-11--1 - 655 0 90 90 90 89 89 565 14% 14%
May - 2021
Work in progress.
No Image
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 30.469 3 2.5 2.5 2.5 2.5 5.5 24.969 18% 18%
May - 2021
Earth work & Sub base in progress. Demand RS. 25 M
No Image
1) Road from Warana Wilayat Khel to Warana Mir Has
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Kohat
HW
30-11--1 30-11--1 - 30-11--1 - 434.741 103.831 0 0 0 0 103.831 330.91 - 24%
May - 2021
06 units 03units completed 03 units in progress. Demand rs. 40 m for Liability 3/6 Units ts approved 2/6 units Submitted to SE 1/6 units TS under prep
No Image
1) Construction of road from Jalal Abad Chowk to Suleman Talab Boraka Kohat .?. Rs; 50.00 M
2. Re-Const: of Sumari Road Kohat  .?.. Rs; 50.144 M
3. Const: of B.T road Khwaja Khel Darsha Khel  .?.. Rs; 106.043 M
4. Const: of B/T Road Sean  .?.. Rs; 69.959 M
5.  Const: of B/T Road Khwaja Pil Road 07 KM   .?.. Rs; 78.595 M
6. Rehab: of Road from Pindi Road to KDA via Shiekhan  .?.. Rs; 80.00 M
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Lakki Marwat
HW
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
May - 2021
4 Km E/Work , Sub Base completed & B/C in progress. Joint survey in progress. Demand Rs: 5 M
No Image
1. Construction / widening / rehabilitation / Dualization Tajori Road to Salman khel Road,
2. Up gradation and strengthing of Shahbaz Khel Road to Biland Khel Road via Wazeer Kila District Lakki Marwat
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Malakand
30-11--1 30-11--1 - 30-11--1 - 50 0 1 1 1 0.753 0.753 49 2% 2%
May - 2021
13- Units - works started Demand Rs. 20 M
No Image
1 PCC Street, Drains & Link road U/C Kharkai ? Rs: 4.00
2 PCC Street, Drains & Link road U/C Kopar ? RS; 4.00
3 PCC Street, Drains & Link road U/C Hero Shah.?. Rs: 4.00
4 PCC Street, Drains & Link road U/C Watair .?. Rs: 4.00
5 PCC Street, Drains & Link road U/C Mehardy.?. Rs: 4.00
6 PCC Street, Drains & Link road U/C GU Khel ? Rs; 3.75
7 PCC Street, Drains & Link road U/C Kot ? Rs; 3.75
8 PCC Street, Drains & Link road U/C Selai Pate ? Rs; 3.75
9 PCC Street, Drains & Link road U/C Sakakot Banda Jat ? Rs; 3.75
10 PCC Street, Drains & Link road U/C Sakakot Jadeed ? Rs; 3.75
11 PCC Street, Drains & Link road U/C Sakakot Kass ? Rs; 3.75
12 PCC Street, Drains & Link road U/C Dargai ? Rs; 3.75
13 PCC Street, Drains & Link road U/C Badraga ? Rs; 3.75
 
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 130.592 38 12.5 12.5 12.5 11.5 49.5 80.092 39% 38%
May - 2021
Structure work completed, road work in progress. Liability : 15 M Demand - Rs 92.60 M.
No Image
1. Rehabilitation of Garlat to Ghari Habibullah (FMR) Road (18-KM) Tehsil Balakot District Mansehra. (PK-30)         
2. Construction & Rehabilitation of Road from Khata Bahi Bala, Chatar Plane Jabar Sydan District Mansehra.     
3. Construction of Road at Tehsil Oghi & Darband District Mansehra          
 
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 176.767 206.643 19.5 19.5 19.5 19.5 226.143 0 100% 100%
May - 2021
12 units - Completed =3 Units Work in progress =9
No Image
  1. Nali Par Hoti road 0.700 KM
  2. NCC rod (Takkar Chowk) to Charandi Killi 0.95 KM
  3. RCC Bridge at JamalGarhi Mardan
  4. 05 KM road formkatti Garhi to Shero Bridge Mardan
  5. Rutam toBircoh road 1.50 KM and Bairoch Chowk to Malanday road 0.20 KM
  6. Baikaro to Kalodheri Pul road 0.5 KM
  7. Bypass Rustam Pul road 0.50 KM
  8. Baioch road to Tashkand Mian Chowk 1.0 KM
  9. Installation of solar Sytam (Solar Work)
  10. Smar Qand Killi to Dhano Chowk to Seni Abad rod 2.14 KM
  11. Const: & Rehab: of Lalmir Killi to Shamilat via Dawajan Kiil toKot Road 3.5 KM
  12. Sultantant Banad Road Haji Gulab Killi Tordher road 1.3 KM
 
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 310.242 33.349 11.5 11.5 11.5 11.5 44.849 265.393 14% 14%
May - 2021
Earth work in progress.
No Image
  1. Road form Excise Office to GT Road Rehman Street
  2. Mughalkai, Misri Banda,  Pirsabad, Bara Band & Zara Mina Road
  3. Katti Khel Rod 2 KM
  4. Rashakai Nowshera
  5. Pirsabaq Nowshera
  6. Abu Bakar Mosque to Tubwell No. 5
  7. Balance work Ameero Gajookhel road 2.5 KM
  8. 1.5 KM Kanakhel Bahader Baba Road
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 50 15 19.9 19.9 19.9 15.37 30.37 15.1 70% 61%
May - 2021
5/5 units - Work in progress. P-II Demand Rs. 11 M
No Image
1. Construction/rehabilitation of Jogani Sarkhana Road.. Rs; 12.171 M
2. Const:/Rehab: of wahid Ghari By-pass road ? Rs: 13.612 M
3. Const:/Rehab: of Essa Khel Hameed Road? Rs: 7.885 M
4. Const:/Rehab: of Garhi Chandan Road at Peshawar? Rs; 9.192 M
5. Const:/Rehab: of saeed Abad/Guli Garhi road? Rs: 7.04 M
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 - 3055.39 0 60 60 60 0 0 0 - -
May - 2021
No Image
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
PS
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 30 0 0 0 - -
May - 2021
No Image
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Shangla
30-11--1 30-11--1 - 30-11--1 - 50 0 22 22 22 13.085 13.085 28 44% 26%
May - 2021
WBM complted
No Image
Behsam Qala Road (2.5 KM)
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Swabi
HW
30-11--1 30-11--1 - 30-11--1 - 173.972 45.1 22 22 22 22 67.1 106.872 39% 39%
May - 2021
(A) 1. Work in progress. 2. Work order issued contractor mobilized. (B) 1. Work order issued contractor mobilized. 2. W/b 02-km. 3. 100% completed. 4. 100% completed 0.8 km W/B. 5. Work in progress. 6. ?do- 7. -do- (C) 1. WBM base course completed& struct:work comp deamnd rs. 50 M
No Image
A. Sub Head:
i-  Anbar to Hund Road 4-Kms (Pk-45)
ii- Pak Kaya to Kunda By Pass Road (1-Km) (Pk-45)
 
B. Sub Head:
Constn: /Reha:/BT/PCC of Roads in Ucs Malak Abad,Kotha, Kalabat,Marghuz, Garr Munara, Bamkhel, Zaida, Kunda, Zarobi, Pabaini, Tankohai, Shahmnasoor & Batakara and Gabeseni in Distt: Swabi.
Sub Work  I.
i- Construction & B/T of Chapai Road (3-Km) (Pk-44)
ii-Construction & B/T of Shah Mansoor Road (0.5Km) Pk-45
iii.Construction & B/T of Shah Mansoor Bye Pass Road (0.5) Km Pk-45
iv.Construction and Black Topping of Jhangi Dher (1-Km) Pk-44)
v.Construction and B/T of  Bherang Road (1-Km)( Pk-44)
vi.Construction and B/T of Bata Kara Road (2-km) ( Pk-43)
vii.Construction and B/T of Chanai Road (2-Km) ( Pk-43)
 
C. Sub Head:
 Constn: of Roads from Hamidul Haq House to Dobian Interchange ( old Toru Road Pk-46-Swabi) (2.0-km)
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 129.581 62.5 21 21 21 21 83.5 46.081 64% 64%
May - 2021
Length 5 Km (12 Units) - 3 Unit completed, 09 Units work in progress.
No Image
1) Jana road (1 Km)
2) Gari to Awishah Road 3 KM (TS 24.314)
3 Peshtoani Road 0.5 Km
4 Taray Road 0.5 KM (TS 3.359)
Part-B (New Work)
Const: o PCC/B/T, 1 Peshmal to Kot Shahi bagh UC Balakot, 2 Pirpatay UC Fatehpur road, 3 Aryanai tkass road etc..
1. Aryanai Kass UC Balakot
2 Dabergi Kol Banr Road
3 Dabergi Dara Road
4  Peshmal to Kot Shahi Bagh U/C Balakot
5 Pir Patary U?C Fatehpur Road
6 Shahi Bagh to Bar Shahgram Road
7 Shamirai Road U?C Tirat (TS 8.778)
8 Tirat Dara Raod (TS 8.774)
 
1759
(OG)
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa
Tank
30-11--1 30-11--1 - 30-11--1 - 22.221 15 0 0 0 0 15 7.221 - 68%
May - 2021
Completed.
No Image
Construction of BT road Gara Shada road (1 Km) Dis
1760
(OG)
190220-Khyber Pakhtunkhwa Rural Roads Improvement and Rehabilitation Project (JICA Assisted)
Provincial
30-11--1 30-11--1 - 30-11--1 - 2025 0 100 90.698 90.698 0 0 0 - -
May - 2021
PC-I cleared by PDWP on 29-06-2020 for onward subm
No Image
1760
(OG)
190220-Khyber Pakhtunkhwa Rural Roads Improvement and Rehabilitation Project (JICA Assisted)
Provincial
30-11--1 30-11--1 - 30-11--1 - 29278.22 0 1000 1000 0 0 0 28278.22 3% -
May - 2021
PC-I cleared by PDWP on 29-06-2020 for onward subm
No Image
1761
(New)
180162-Special Repair & Maintenance of identified Provincial Highways through Perofrmance Based Maintenance (PBM) Pilot Project under Provincial Roads Improvement Project (ADB Assisted)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 - 1092.27 0 10 0 0 0 0 1082.27 1% -
May - 2021
Approved
No Image
1. Mardan Estern Western Bypass
2. Malam Jaba Road
3. Matta Fazal Banda Road
1762
(New)
180462-F/S for Khyber Pakhtunkhwa Roads Network (Master Plan)
Provincial
PRIP
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 10 10 0 0 0 0 - -
May - 2021
Deleted in Project Steering Committee.
No Image
1763
(New)
180589-Feasibility Study on Khyber Pakhtunkhwa Rural Roads Improvement & Rehabilitation Project (JICA Assisted) (Phase-II)
Provincial
PMU
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 10 10 0 0 0 0 - -
May - 2021
PC-II (78.5 M) deferred in 22/10/2020 PDWP for fulfilling the necessary formalities as required for donors assisted projects. Concept paper submitted to HQ JICA Japan for vetting (response awaited)
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 5 0 0 0 0 0 0 5 - -
May - 2021
Tender under process
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 39.92 0 0 0 0 0 0 39.92 - -
May - 2021
Work started
No Image
  1. Ghari Sher Ahamad Killa road
  2. Zaker Kheli road to Nakam Majid
  3. Habed Jani Kheli road to Haved village
  4. Haved Jnai Khel road to Tope Haved
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
May - 2021
work started Demand Rs. 20 M
No Image
1 Ganthar Road (1 KM)
2 Gangwal Road (1 KM)
3 Batila Road (1 KM)
4 Pashto Road (1 KM)
5 Jamber Road  (1 KM)
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Buner
HW
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
May - 2021
02- Units work order issued demand Rs. 10 M
No Image
1. Construction, Improvement, Widening & Blacktopping of Badir Asharai Road, District Buner (02 KM) PK-22
2. Construction, Improvement, Widening & Blacktopping of Dandikot Road, District Buner (01 KM) PK-22
 
 
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Charsadda
HW
30-11--1 30-11--1 - 30-11--1 - 187.347 0 0 0 0 0 0 187.347 - -
May - 2021
work order issued work started Demand Rs: 50 M
No Image
1. Const: & B/T of road from Thana Bazar Matta to Minoroa? Rs; 15.130 M
2. Const: & B/T of road from Bakra road to Yousaf Khan Qilla  ? Rs; 9.940 M
3. Const: & B/T of road  from Hasanzai road to Tarhari Shabqadar ? Rs; 6.750 M
4. Const: & B/T of road from  Saddar Ghari to Katozai ? Rs; 8.960 M
5. Const: & B/T of road from Nasratzai to Attaki via Muqbara i/c link road  ? Rs; 100.00 M
6. Const: & B/T of road Main Essa to Ghigi Qilla ? Rs; 5.220 M
7. Const: & B/T of road from Haryan torad to Tarkha ? Rs; 6.920 M
8. Const: & B/T of road from Speeni to Matta ? Rs; 9.480 M
9. Const: & B/T of road from Hjangyano Banda Dalazak to Rashakai ? Rs; 9.730 M
10. Const: & B/T of road from Peshawar road to Main Qilla Shabqdar ? Rs; 3.140 M
11. Const: & B/T of road from Thana Bazar Matta to Sarhad Koroona Shabqadar  ? Rs; 6.210  M
12. Const: & B/T of road from Kabe to Nazar Ghari ? Rs; 5.780 M
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Chitral
30-11--1 30-11--1 - 30-11--1 - 32.26 0 0 0 0 0 0 32.26 - -
May - 2021
Approved
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 32.26 0 0 0 0 0 0 32.26 - -
May - 2021
03 units - work order issued Deamnd Rs. 22.21 m
No Image
  1. Bumborte Kandisar Road
  2. Rumboor Road
  3. Birir Road
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 150 0 0 0 0 0 0 150 - -
May - 2021
16 Units 08 Units in progress 08 Units Tender in porcess Demand Rs: 50 M
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Hangu
30-11--1 30-11--1 - 30-11--1 - 100 0 0 0 0 0 0 100 - -
May - 2021
E. Work in progress. Demand Rs: 20 M
No Image
1. Const: of Middle School Saru Khel Road U/C Darsamand
2. Const:  of Tabook Banda Road U/C Darsamand
3. Const: & B/T of Toheed Abad Croad U/C Doaba
4. Const: of Gur Baya PCC road U/C darsamand
5. Const: & Rehab: of Kanda Chapri Karbogha road U/C Karbogha Road
6. Const: & Rehab: of Naryab Town road U/C Naryab-I
7. Const: of village road Gandaria U/C Dalan
8. Const: & Rehab: of Torawari Madrasa road U/C Torawari
9. Const: of Jadeed Banda U/C Tora Wari
10. Const: of Sawan Banda Road U/C Naryab-I
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Haripur
HW
30-11--1 30-11--1 - 30-11--1 - 200 0 15 15 15 15 15 185 8% 8%
May - 2021
49 units Work Started
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Karak
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
May - 2021
02 Componenets work in progress Demand Rs: 30 M
No Image
1 Inzer More to Lakki Banda 1.3 KM
2 KPHA road Jatan Banda 1.9 KM
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Kohat
HW
30-11--1 30-11--1 - 30-11--1 - 30 0 0 0 0 0 0 30 - -
May - 2021
Work order issued demand Rs. 7 M
No Image
Const: / Rehab: of B/T road from Shadi Khel to Kamal Khel Road at PK-80 Kohat
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Kohistan
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 5 0 0 145 3% -
May - 2021
16 Units - work order issued
No Image
06 Nos Packages
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 947.995 0 96 96 96 79.044 79.044 851.995 10% 8%
May - 2021
work order issued
No Image
  1. Cosnt:/Imp:/Reahb: of Main Swabi road toRashka village
  2. Cosnt:/Imp:/Reahb: of Gumbat Hospital to Battai Koroona
  3. Cosnt:/Imp:/Reahb: of Charssada road to Jamsheed Khan Killi
  4. Cosnt:/Imp:/Reahb: of Parkho Kiili road
  5. Cosnt:/Imp:/Reahb: of MasterMandi toTehakadar Koroona Main Jan Killi and Military Farm to Charssada road to Haji Abad Road.
  6. Cosnt:/Imp:/Reahb: of  road from Lund Khwar to Fazale Abad Pul Killi and Mote Banda
  7. Cosnt:/Imp:/Reahb: of  road from Hathyan to Lund Khwar and Lund Khawar bypass road
  8. Cosnt:/Imp:/Reahb: of  road from Umar Abad to Sanga Gul Mera raod
  9. Cosnt:/Imp:/Reahb: of Bakhshali interchange to Shakh Killi Bakhsali Charguly road (Package-I Bridge)
  10. Cosnt:/Imp:/Reahb: of Bakhshali Interchange to Shakh Killi Bakhshali Charguy road (Package II 5.00)
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 483.64 0 44 44 44 18.955 18.955 439.64 9% 4%
May - 2021
work started Demand Rs: 200 M
No Image
1. Palosai adda to Islmia Madrassa and sourrounding area? Rs: 19.950 M
2. Masjid Sadar to Masjid Ashaab Haji Khyber Khan Palosai Talarzai Maghdarzai and link road? Rs: 30.00 M
3. Const: of road & street at UC 30, 31, & 32? Rs: 24.960 M
4. Const: of road & street at UC 33, 34, & 35? Rs: 24.960 M
5. Const: of road in saeed Abad No. 2, Bajuri Street, Afghan Colony Canal Side, Sardar Colony Mateen Colony and sorrounding area? Rs: 25.090 M
6. Const: of link road form ring road to Hassan Ghari, Kifayat Hujra road Ghari Balaoch and Ajmal CNG road, Lakhar Kalay road and Sourrounding area? Rs; 24.910 M
7. Rehab:/Reconst: of canal road form Dalazak rod toray Kababi to GT road with sorrounindg area? Rs; 24.940 M
8. Rehab:/RE-Const: of Muhammad Abad road, Kishwar street road Gulbahar i/c various streest in UC-I? Rs; 23.780 M
9. Const: of Kagawala Afridi Abad Road? Rs; 13.300 M
10. Const: of Marozai Ghari Habib Khan road? Rs; 12.460 M
11.  Const: of Mohalla Cheena road with PDM link? Rs; 5.180 M
12. Const: of Yaqoob Colony road opposite kohat bus stand? Rs; 7.180 M
13. Rehab: of road from Ahmad Khel Canal to Kohat Road? Rs; 7.240 M
14. Const; of Marozai Link Road.?. Rs; 4.630 M
15. Const:/Rehab: of Naguman Karyana road form Batayan to Niamy? Rs; 70.030 M
16. Const:/Rehab: of road form Gulli Bagh Kaniza? Rs; 16.990 M
17. Const:/Rehab: of road form Janas Masjid to Subhan Khan koroona Larma? Rs; 14.290 M
18. Const:/Rehab; of road form Benazair University to Ghari Khan Baba i/c Link road? Rs; 4.060 M
19.  Const: /Rehab: of Barbar Opazai Road? Rs; 14.550 M
20. Const:/Rehab: of road from larama Chowk to Mandra  Khel? Rs: 17.600 M
21. PCC work internal in Phandu Sabzi Mandi,,, Rs: 21.480 M
22. Road form Naguman Chowk Charssadda road to Lachi Koroona Qadeem Abad Dub at Ghari Chiragh Shah U/C Gul Bela.?. Rs: 40.060 M.
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Provincial
30-11--1 30-11--1 - 30-11--1 - 2000 0 120 120 120 0 0 0 - -
May - 2021
Approved.
No Image
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Swabi
HW
30-11--1 30-11--1 - 30-11--1 - 152.12 0 0 0 0 0 0 152.12 - -
May - 2021
12 units work order issued Demand Rs. 30 M
No Image
    1. Dandoka Lar (Near Umar sher House)Yar Hussain  Road(01-km)
    2. Garai Lar Yar Hussain Road  (01-km) PK-46
    3. Repair / Rehabilitation of Dobian Road   PK-46
    4.  Karimullah Kotey Sadri Qadeem Road (01-km) PK-46
    5.  Malakzo Road    (01-km) PK-46
    6.  Narai Lar Rohanay Road     (01-km) PK-46
    7.  Nazar Tarkha  link Road    (02-km) PK-46
    8.  Speen Kani village Road   (01-km) PK-46
    9.  Rep:& Reh:of linl Road to captain Kernal Sher Khan village PK-47
    10.  Ground Lar Union Council Zaida
    11.  Seen Lar Union Council Zaida
    12.  Ground Lar Union Council Beka Swabi
 
1764
(New)
180615-Construction of Roads & Bridges on need Basis
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 238.4 73759 17.179 17.179 17.179 17.179 73776.179 0 100% 100%
May - 2021
08 Units 03 unit completed 05 in progress
No Image
  1. PCC Kabal Koo Road 2 KM S/T Barko Kandawgai road (TS 15.599)
  2. BTR Taangar road 2 KM
  3. PCC Saidrara torad S/T Sarkhona Road Sakhra
  4. PCC Gal Shah Road S/T Asharay Dambara road
  5. BTR Chuprail Balasoor road S/T Bahadar Banda Road , and JaGRAM ROAD
  6. PCC Nall to Bodigram Road S/T Bulkarai Dandarai road (TS 10.820)
  7. PCC Kass Duraskhela to Brinjal road 1 KM
  8. BTR Dandarai road 1.5 KM S/T Collee Road Matta (TS 14.834)
1765
(New)
190221-Rehabilitation of Flood Damages Rural Roads under Counter Value Fund (CVF Japan Assisted)
Provincial
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
May - 2021
Concept paper approved by CDWP and hiring of Consultant. Completion : June-2021.
No Image
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
PC-II Approved for Rs.40.55 M (Umbrella) XEN Bannu Focal Person for Peshwar , Hangu , D I Khan , Bannu financial Bid Submitted to DST
No Image
  1. RCC Bridge at Lhaisoor Marwath Canal road
  2. RCC Bridge at Kachkot Canal System at Lora canal
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
Buner
HW
30-11--1 30-11--1 - 30-11--1 - 40.55 0 0 0 0 0 0 40.55 - -
May - 2021
6 Bridges ( 2 in buner , 1 in all other ) Financial opening of consultants in progress XEN Buner focal Person for Buner , Malkand , Dir Upper , Shangla, dir Lower
No Image
1. Construction of RCC Bridge (Span 60 M) at Bhai Kalay Jokhela Jowar Road, District Buner PK-20
2. Construction of RCC Bridge (Span 30 M) at Village Rega UC Rega, District Buner PK-21
 
 
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
PC-II Approved for Rs.40.55 M (Umbrella) (XEN Bannu Focal Person)
No Image
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
Financial Bids opened on 24-04-21 XEN Buner Focal Person
No Image
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
PC-II Approved for Rs.40.55 M (Umbrella) Focal Person XEN Buner
No Image
1766
(New)
190598-Construction of 10 Nos RCC Bridges in Khyber Pakhtunkhwa (On need basis)
Hangu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2021
PC-II Approved for Rs.40.55 M (Umbrella) (focal Person XEN Bannu)
No Image