Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85 | 18.44 | 4.5 | 4.5 | 4.5 | 4.499 | 22.939 | 62.06 | 27% |
27% May - 2021 |
08- components
Work in progress on all units.
Demand RS. 20 M |
No Image |
1. Indus Highaway Jehangari Inzar Mor Link Road? Rs; 5.85 M
2. Karak Surdog Road 18-KM.?. Rs; 9.80 M
3. Serak Odin Shah Road 6-KM .?. Rs; 9.80 M
4. Ahmad Abad Khojaki Killa Link Road Mohabati Killa 8.5 KM.?. Rs; 8.24 M
5. Tangori Sar Saraj Bab I/C Wanki Siraji Khel Dabli Lawagher Link Road 11- KM.?.. Rs; 17.02 M
6. From indus Highway via Dabli Lawagher to Faqir Abad 10-KM ? Rs; 20.917 M
7. Ali Khel Chowk via Palosa Sar to Ghoundi Shamshaki Road i/c Link Road to Gororhi Char Khel 7-KM.?. Rs; 14.041 M
8. Ali Khel Chowk to Zabi Chani Khel Road 5-KM ? Rs; 5.041 M | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4.389 | 2.206 | 2.5 | 2.5 | 2.5 | 0 | 2.206 | 0 | 100% |
50% May - 2021 |
RCC work for pile protection completed. Wire crate constn in progress. Notice issued to the contractor for the delay work. |
No Image |
Restoration of damages and protection works o | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.541 | 34.883 | 4 | 4 | 4 | 3.879 | 38.762 | 5.658 | 87% |
87% May - 2021 |
Scheme completed
Rs. 4 M required to clear the contractor laiblity. |
No Image |
1. Rehabilitation of Causeway at Warsak Jamrud road on sufaid Khawar? Rs: 19.191 M
2. RehaBbilitation of takhatabad Road District Peshawar? Rs: 25.35 M | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 690.864 | 0 | 30 | 30 | 30 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
PS |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Swabi HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.071 | 17.538 | 0 | 0 | 0 | 0 | 17.538 | 0 | - |
100% May - 2021 |
Completed. |
No Image |
Jandah Pabani road PK-35 | |||||||||||||||||||
1754 (OG) |
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.854 | 27.204 | 0 | 0 | 0 | 0 | 27.204 | 9.65 | - |
74% May - 2021 |
9/9units completed. |
No Image |
1) Construction of RW on Taran road UC Taran road (TS 3.454)
2 Qambar to Fizagat Bypass road (TS 0.974)
3 Lalkoo Steel Bridge (Protection work) (TS 3.077)
4 Kuz Lalkoo road (Protection work) (TS 3.127)
5 Chail Shinkoo Bashigram Road (TS 7.440
6 Bandai to Sigram Road (Protection work)
7 Meramai Madyat RCC Culvert (TS 0.821)
8 Spardada Steel Brdige (Protcion work)
9 Proection work of Landikass Janu Bridge (TS 0.910) | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.76 | 26.615 | 4.5 | 4.5 | 4.5 | 4.5 | 31.115 | 16.645 | 65% |
65% May - 2021 |
3/3 units -work in progress.
2. EW 70 % Structure work complted
Demand Rs. 10 M |
No Image |
1) Pandu Thana road District Abbottabad
2 Widening/Carpetting of Bio - pull Mohri Road Abbottabad
3 Jhangi Khoja Banda Qazi UC Jhangi Banda Qazi .?.?.?. TS 2.225 | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70.99 | 27.431 | 15 | 15 | 15 | 15 | 42.431 | 28.559 | 60% |
60% May - 2021 |
Length 1 Km - earth work 40% completed.
Demand Rs. 20 M |
No Image |
| |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 16.8 | 5.5 | 5.5 | 5.5 | 5.499 | 22.299 | 0 | 100% |
100% May - 2021 |
Length 2 Km - 95% work completed.
Demand Rs. 2 M |
No Image |
Thakot Banna road (29 Km), Battagram | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Charsadda HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.674 | 126.982 | 9.5 | 9.5 | 9.5 | 9.5 | 136.482 | 0 | 100% |
100% May - 2021 |
Completed (Package-1 (length - 5 Km (12 ft). Package-II, III & IV in progress.
Demand Rs: 35 M |
No Image |
1. Package-I: 06 No. Different roads (4.95 Km)? Rs: 57.674 M
2. Package-2: 07 Nos Different roads ? Rs: 59.376 M
3. Package-3: 07 Nos Different roads ? Rs: 59.591M
4. Package-4: 05 Nos Different roads ? Rs: 49.400 M | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15 | 3 | 2 | 2 | 2 | 2 | 5 | 10 | 33% |
33% May - 2021 |
Work started.
Demand Rs. 3.7 M,,,
Road way cutting in progress. |
No Image |
Rehabilitation/repair of Arkari Valley road Chitral | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40 | 9.996 | 1 | 1 | 1 | 1 | 10.996 | 29.004 | 27% |
27% May - 2021 |
B/Course & Asphalt completed.
Structure work & E/Work in progress |
No Image |
Improvement/rehabilitation of various roads i | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 5 | 5 | 5 | 5 | 5 | 15 | 25% |
25% May - 2021 |
Earth and structure work completed.
Demand Rs. 20 M |
No Image |
i) Constn:/Widening of Adhokey Bala road PK-9 | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Haripur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 642.572 | 0 | 32.75 | 32.75 | 32.75 | 32.75 | 32.75 | 609.822 | 5% |
5% May - 2021 |
Work in progress on all 62 units. |
No Image |
1) Constn:/reh: of link road Chappra to Kalal | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 29.241 | 6.701 | 4 | 4 | 4 | 4 | 10.701 | 18.54 | 37% |
37% May - 2021 |
02-components
i) Earth work 80% completed. S/B, WBM & Masonry work 80% completed.
Demand RS. 15 M |
No Image |
1.
i. GPS Wadan Khel to GHSS Dabli Lawagher i/c Link road of Naiz Wali Koroona? Rs; 19.250 M
ii. Nawab Khan Koroona to Yousaf Khan Koroona (out of saving) 0.4-KKM
2. Const: of BTR from GHSS to Sam Koroona Dabli Lawagher PK-41 Karak? Rs; 9.991 M | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.593 | 1 | 1 | 1 | 0 | 16.593 | 7.407 | 70% |
66% May - 2021 |
Completed. |
No Image |
| |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 677.291 | 275.378 | 21 | 21 | 21 | 21 | 296.378 | 380.913 | 44% |
44% May - 2021 |
14- Units
Work in progress on all units. |
No Image |
| |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 292.329 | 67.178 | 59.75 | 59.75 | 59.75 | 36.893 | 104.071 | 165.401 | 43% |
36% May - 2021 |
05 Packages-
02 Packages Completed
03 Packages work In progress.
Deamnd Rs. 50 M |
No Image |
1. Various roads in PK-66.?. Rs: 30.00 M
2. Various roads in PK-69 & 70.?. Rs: 45.503 M (TS 14.603)
3. Various roads in PK-68.?. Rs: 30.00 M (TS 4.667)
4. Various roads in PK-68 & 69.?. Rs: 48.10 M (TS 12.164)
5. Various roads in PK-79.?. Rs: 40.00 M | |||||||||||||||||||
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2131.395 | 0 | 75 | 75 | 75 | 0 | 0 | 0 | - |
- May - 2021 |
2nd Rev approved. |
No Image |
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
PS |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 37.5 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Swabi HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
DCE for Rs.50.125(M) submitted for approval. |
No Image |
1755 (OG) |
160622-F/S, Design and Rehabilitation of C&W roads in Khyber Pakhtunkhwa |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 63.673 | 49 | 0.27 | 0.27 | 0.27 | 0.269 | 49.269 | 14.403 | 77% |
77% May - 2021 |
02- Units
1- Completed
1- Work in progress. |
No Image |
1) Construction of road from Awarwi to Spero 2 KM (TS 24.532)
2 Const: of Road form B/T of Balasoor Danderai 02 KM (TS 26.442) | |||||||||||||||||||
1756 (OG) |
170173-Provision for Liabilities of Land Compensation |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.413 | 0 | 0 | 0 | 0 | 0 | 0 | 0.413 | - |
- May - 2021 |
Approved. |
No Image |
i) Government versus Arshad Mehmood & Oth | |||||||||||||||||||
1756 (OG) |
170173-Provision for Liabilities of Land Compensation |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.138 | 0 | 74.579 | 74.579 | 74.579 | 74.579 | 74.579 | 73.559 | 50% |
50% May - 2021 |
Approved.
Demand balance allocation. |
No Image |
Land Compensation of "Approach road from NCC road | |||||||||||||||||||
1756 (OG) |
170173-Provision for Liabilities of Land Compensation |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.419 | 0 | 1.571 | 1.571 | 1.571 | 1.262 | 1.262 | 40.848 | 4% |
3% May - 2021 |
Payment to made to the owner as per Court Order |
No Image |
1756 (OG) |
170173-Provision for Liabilities of Land Compensation |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 496.839 | 422.26 | 74.579 | 74.579 | 74.579 | 0 | 422.26 | 0 | - |
- May - 2021 |
Completion : June-2021. |
No Image |
1756 (OG) |
170173-Provision for Liabilities of Land Compensation |
PS |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Contractor liabilities |
No Image |
1757 (OG) |
170521-F/S & Dualization of Mardan-Swabi Road (ADB Assisted) |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1337 | 12.5 | 220 | 220 | 220 | 65.287 | 77.787 | 1104.5 | 17% |
6% May - 2021 |
Work in progress. |
No Image |
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.75 | 16.807 | 7 | 7 | 7 | 7 | 23.807 | 23.943 | 50% |
50% May - 2021 |
Work started (2 units). |
No Image |
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
| |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50.95 | 0 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 50.45 | 1% |
1% May - 2021 |
Bridge- Piles completed.
Demand Rs. 20 M |
No Image |
Main Kacha road to village Bazida Kokal Khel Bharat Bannu | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 2 | 2 | 2 | 2 | 2 | 48 | 4% |
4% May - 2021 |
Demand Rs. 30 M?.. 5 units , Earth work completed..
Demand Rs. 20 M |
No Image |
1 Gnatar Road (1 KM)
2 Gangwal Road (1 KM)
3 Bateela Road (1 KM)
4 Pashto Road (1 KM)
5 Jambera Road (1 KM) | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Charsadda HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 56.54 | 0 | 3 | 3 | 3 | 3 | 3 | 53.54 | 5% |
5% May - 2021 |
Work in Progress
Deamnd Rs. 20 M |
No Image |
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003 M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
| |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.673 | 0 | 4.896 | 4.896 | 4.896 | 4.896 | 4.896 | 80.777 | 6% |
6% May - 2021 |
(14 Units)
08- Units completed
06- units in progress
TS Pending |
No Image |
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 8 | 8 | 8 | 8 | 8 | 42 | 16% |
16% May - 2021 |
Procurement completed
09 Units
04 Units in progress
Earth work, structure work completed.
Demand Rs. 20 M |
No Image |
1 Kargha ROad
2 Chenargay Road
3 Bandgari Road
4 Wahdat Road
5 Srogal Road
6 Balo Khan Road
7 Lawanda Road
8 Bokrai Road
9 Manai Sukai Road | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 49.5 | 1% |
1% May - 2021 |
Work order issue.
Demand Rs. 20 M |
No Image |
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 21.805 | 21.805 | 21.805 | 10.44 | 10.44 | 28.195 | 44% |
21% May - 2021 |
Work order issued. Layout given. |
No Image |
1. Const: of road and rain Petao Khel Remaining Porotion Kahi 1.21 KM
2. Const: of B/T Road Shahowam to Khano Talab 0.731 KM UC Raisan
3. Const: of PCC Road Hangu Lal Muhammad Khawaja 0.975 KM U/C M. Khawaja
4. Rehab: of Sukari Road form Samana Road to FC Check Post (Balance portion) 0.640 KM U/C Gunjana Killi
5. Rehab; & Const: of Bakaro Banda Road Kahi 0.304 KM U/C Kahi
6. Const: of Link B/T road to GGHS Warsta from Samana Road to Warasta Road 0.121 KM U/C Gunjana Killi | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Haripur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 421 | 0 | 79 | 79 | 79 | 73 | 73 | 342 | 19% |
17% May - 2021 |
Work in progress. |
No Image |
Roads in PK-42 Ghazi District Haripur | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.74 | 0 | 2 | 2 | 2 | 1.4 | 1.4 | 10.74 | 16% |
11% May - 2021 |
Work in progress.
Demand
Rs. 2.5 M for completion |
No Image |
Construction of Ghundi Killi Ahmad Abad road (rema | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90 | 0 | 20.969 | 20.969 | 20.969 | 16.86 | 0 | 0 |
May - 2021 |
Completed. 1.5 Km shingle road in progress.
And work order issued for remaing unit work started.
Deamnd Rs. 25 M |
No Image | |
1 Zaid Kher Road form Daingozia to Ashanabair 2 KM
2 Zaid Kher Road form Daingozia to Ashanabair (Balance work) | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 0 | 13.5 | 13.5 | 13.5 | 6 | 6 | 16.5 | 45% |
20% May - 2021 |
03- Units - Work in progress. |
No Image |
1 Cont: Widening & Rehab: of road at Ghareeb Abad U/C Upper Batkhela (1 KM)
2 Cont: Widening & Rehab: of road at Sangeena U/C Upper Batkhela (1 KM)
3 Cont: Widening & Rehab: of road at Fazal Abad U/C Allahdhand (0.6 KM) | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Mansehra HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.25 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 47.75 | 7% |
7% May - 2021 |
11 - Units
1- Unit completed.
5- Units Earth work in progress.
1 Structure Work in Progress, Road Work in Progress.
2 "E/Work Completed.
Structure Work in Progess."
3 E/Work Completed & Structrue Work in Progress.
4 Work Not Yet Started.
Road & Structure work in Progress.
5 Road & Structure work in Progress.
6 "Earth Work Completed.
Road Work in Progress."
7 Completed.
8 Work in Progress.
9 Work Order Issued
10 Work Order Issued
11 Work Order Issued
11 Tender floated on 18/03/2021
Liability : 20 M |
No Image |
1) Shoukat Abad to Tatar raod (1.5 Km).?.?.. TS 4.755
2 PCC road Nullah Chinarkot.?.?... TS 2.791
3 Shahkot Bala
4 Karmatee
5 Boz Bela.?.?. TS 2.432
6 Bawar Khan
7 Belian to Trawara
8 Qazi Abad (Battai).?? TS 4.950
9 PCC Link road Buttle
10 PCC link Mahandri
11 PCC link road Garhi Habibullah
| |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.78 | 25.208 | 36.5 | 36.5 | 36.5 | 36.5 | 61.708 | 22.072 | 74% |
74% May - 2021 |
5 units -
Structure work in progress. |
No Image |
| |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 321.11 | 40.78389 | 29 | 29 | 29 | 29 | 69.78389 | 251.326 | 22% |
22% May - 2021 |
12 units - SST Road- Earth work in progress. |
No Image |
| |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 49.5 | 1% |
1% May - 2021 |
5 units- Work In progress.
Demand Rs. 20 M
Liability Rs: 10 M |
No Image |
Const: of road at Ucs Mahal Teria-2, Khalisa-2, Hassan Ghari-1 & 2, & Shahi Bagh Peshawar... | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2581.105 | 598.58 | 60 | 80 | 60 | 0 | 598.58 | 0 | - |
- May - 2021 |
Work started. |
No Image |
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Swabi HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 165.39 | 0 | 5 | 5 | 5 | 5 | 5 | 160.39 | 3% |
3% May - 2021 |
09- Units
Work in progress.
Demand RS. 35 M |
No Image |
1) Sogandai road (1 Km)
2) Gul abad .?.. TS (8.079)
3 Ismail Abad Kut Kani Road
4 Kalabat Road .?.. TS (15.845)
5 Kotha BHU Janzgha .?.. TS (10.779)
B. (Pk-47)
i. Tarakai Dojangai Road U/C Tarakai (01 Km)
ii- Qadamay Shaheeda Tarakai Road U/C Tarakai (01-km) .?.?.?. TS (11.981)
iii. Permoli Road U/C Permoli (02 km)
iv. Constn: and B/T of Kalu Khan Road U/C Kalu Khan (02 Km) | |||||||||||||||||||
1758 (OG) |
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 715.12 | 0 | 314 | 314 | 314 | 195.505 | 195.505 | 401.12 | 44% |
27% May - 2021 |
38 - Units
Earth work, Sub Base & Structure work in progress on all units.
Demand Rs: 50.00 M |
No Image |
1) Qalagay Guldheri road (1 Km) and Surey Julaitot | |||||||||||||||||||
1759 (OG) |
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.81 | 11.41 | 3.279 | 3.279 | 3.279 | 3.279 | 14.689 | 75.121 | 16% |
16% May - 2021 |
Work in progress
Demand Rs. 5 M |
No Image |
1 Kaseel Batoini via Sareela 3 KM
2 Makool Danan to Kagian Danna road, Tatreela road, Kholianroad and BT of Chanmari Tajwal road
3 Barbeen (Boi) AJK (Gotha Suspension Bridge) link road 0.5 KM | |||||||||||||||||||
1759 (OG) |
170587-Upgradation & Strengthening of C&W Roads in Khyber Pakhtunkhwa |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18.609 | 38.2 | 12 | 12 | 12 | 12 | 50.2 | 0 | 100% |
100% May - 2021 |
Work started.
Demand Rs. 30 M |
No Image |
i. Kotka Ibrahim Khel via Samanda Kala 1.4 KM
ii. Kotka Purana Shikhan via Sarwarngi Aada 1.4 KM
iii. Samdri road
iv. Kotka Musa Khan Yark Khel Mandan road 0.33 KM | |||||||||||||||||||