Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1714 (OG) |
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1498.019 | 491.425 | 50 | 75 | 75 | 75 | 566.425 | 956.594 | 36% |
38% May - 2021 |
03- Packages
Package -I (5Km) completed.
Package-II& III in progress.
Demand - Rs 1218 M. |
No Image |
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge) | |||||||||||||||||||
1715 (OG) |
140620-Re-construction of Bridge at Tor Warsak Daggar & widening/improvement & BT of 18 KM leftover portion of Swarai Pir Qilla Puran Road, District Buner. |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1017.223 | 285.579 | 50 | 99 | 99 | 99 | 384.579 | 681.644 | 33% |
38% May - 2021 |
Pack-1 Bridge - completed,
Road in Pack-1 (6 Km) -
Pack-II = (06Km)
Pack=III (6.85 Km)
sub base, Embankement, Sub grade WBM, Wearing Course, R/wall, & S/Work in progress. |
No Image |
Package-I (Reconstruction of Bridge at Tor Warsak Daggar)
Package-II (BT/Widen of 18 KM Leftover portion of Swarai Pir Qilla Puran Road Buner)
Package-III (6 KM)
Package-IV (6.85 KM) | |||||||||||||||||||
1716 (OG) |
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner |
Buner PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1464.977 | 94.575 | 50 | 50 | 50 | 50 | 144.575 | 1320.402 | 10% |
10% May - 2021 |
03-Packages)
Pack-1 = (5Km)
Pack-II =(6Km)
Pack--III (Bridge)
Pack-1 sub base, Embankement, Sub grade WBM, Wearing Course, R/wall, & S/Work in progress. Bridge in pack-III not yet started. |
No Image |
Package-I .?. 5 - KM Road
Package-II.?. 6 - KM Road
Package-III.?. Bridge | |||||||||||||||||||
1717 (OG) |
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 KM, District Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2257.599 | 1766.373 | 196.226 | 196.226 | 196.226 | 196.226 | 1962.599 | 295 | 87% |
87% May - 2021 |
35 Km (3 Packages)
25 Km BT completed.
Brdiges in progress.
Completion : June-2021. |
No Image |
Package-1 (12 Km)? Rs. 321.796 M
Package-2 (12 Km)? Rs. 391.766 M
Package-3 (11.250 Km)? Rs. 366.934 M | |||||||||||||||||||
1718 (OG) |
160630-F/S, Design and Construction of 2 No. Flyovers on Mingora Kanju Road SH: Mingora Bypass and Kanju Chowk, District Swat |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1198.1 | 973.594 | 105.126 | 105.126 | 105.126 | 105.126 | 1078.72 | 119.38 | 90% |
90% May - 2021 |
02 Nos load Test completed.
Working Piles completed
(Mingora Flyover)
Girdar 15 Nos cated. |
No Image |
Mingora Bypass and Kanju Chowk. | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% May - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 0 | 0 | 0 | 0 |
May - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |
Bridge | |||||||||||||||||||
1721 (OG) |
190559-F/S, Detailed Engg and Constructioin of Matta Bypass Road (6 Km), Swat (Bypass road (6 Km) at Ditpanai to Baidara Tehsil Matta District Swat). |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 474.946 | 466.5 | 35 | 35 | 35 | 35 | 501.5 | 0 | 100% |
100% May - 2021 |
5/8 Km overlapping with swat Expressway.
Work in progress.
Revised Pc-1 is under preparation. |
No Image |
Package-I.?. 3-KM
Package-II.?. 5-KM | |||||||||||||||||||
1722 (OG) |
190561-Improvement and treatment of shoulders of Matta Fazal Banda road (23 Km), Swat |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147 | 170 | 80 | 80 | 80 | 80 | 250 | 0 | 100% |
100% May - 2021 |
Work awarded to M/S Amanullah & Co.
PCC Should 70% completed & further is in progress. |
No Image |
1723 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 382.725 | 40 | 40 | 40 | 40 | 422.725 | 267.274 | 61% |
61% May - 2021 |
Substantially completed. Shifting of Electric pole in progress. |
No Image |
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM | |||||||||||||||||||
1724 (OG) |
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir. (SDG) |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 410.621 | 308.938 | 80 | 80 | 80 | 80 | 388.938 | 21.683 | 95% |
95% May - 2021 |
Bridge (180 mtr) - 21 Piles completed. Transum,Girder launching, Deck Slabe, Abutment completed.
L/S, R/s,R/Wall & protection work is in progess. |
No Image |
1725 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1792.052 | 6.469 | 6.469 | 6.469 | 6.469 | 1798.521 | 0 | 100% |
100% May - 2021 |
Length 36 Km -
07- Packages
subtantially completed.
Completion : June-2021. |
No Image |
1) Package-1 Km-0 to 9 (9 Km) Chukiatan to Sharmaye
2) Package-2 Km-9 to 16 (7 Km) Sharmaye to Chinaran
3) Package-3 Km-17 to 24 (7 Km) Chinaran to Salol
4) Package-4 Km-24 to 31+797 m (7.8 Km) Salol to Patrak
5) Package-5 3 Nos bridges
6. Package-6 02 Nos Bridges
7. Package-7 33.979 Km Chukiatan to Patrak | |||||||||||||||||||
1726 (OG) |
140829-Improvement of 25 KM left over portion of Chukiyatan - Barawal - Shahi Road, District Dir (Upper). |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 973 | 399 | 50 | 50 | 50 | 50 | 449 | 524 | 46% |
46% May - 2021 |
Length 25 Km.
04 - Packages.
Sub Base,Site cutting, WBM, Wearing course, R/Wall, Drain & Shulder in progress. |
No Image |
Package-1 (Barawal Bandi to Jan Bati) 8-KM
Package-2 (Jan Bati to Shaltalo) 8-KM
Package-3 (Shaltalo to Marawaro) 5-KM
Package-4 (Marawaro to Shahi Top) 4-KM | |||||||||||||||||||
1727 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1131.489 | 947.075 | 50 | 50 | 50 | 50 | 997.075 | 134.414 | 88% |
88% May - 2021 |
Length 7.1 Km - Pack-1, 2 and 3 - completed.
Pack-IV bridge in progress. |
No Image |
Package-1 Muree Chowk to Board Office (3.1 KM)
Package-2 Board Office to Dharkan Bridge (4.0 KM)
Package-3 (04 Nos Bridges) | |||||||||||||||||||
1728 (OG) |
140877-Construction of Haripur Bypass Road (23-KM). |
Haripur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4982.922 | 3269.313 | 100 | 198 | 198 | 198 | 3467.313 | 1613.609 | 68% |
70% May - 2021 |
Length 23 Km -
(07-Packages) sub base, sub grade, ABC, AWC, in progress.
Demand - Rs 2386.047 M. |
No Image |
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover | |||||||||||||||||||
1729 (OG) |
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur |
Haripur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2232.195 | 319.581 | 60 | 60 | 60 | 60 | 379.581 | 1852.614 | 17% |
17% May - 2021 |
package-I Completed
Package 2 & 3 in progress
Package 4 work stoped due to non availaitliy of drawing |
No Image |
Package-1 (9-KM)
Package-2 (9-KM)
Package-3 (9-KM)
Package-4 (8-KM) | |||||||||||||||||||
1730 (OG) |
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km) |
Haripur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1274.72 | 7.5 | 10 | 10 | 10 | 10 | 17.5 | 1257.22 | 1% |
1% May - 2021 |
work started on 1st scheme |
No Image |
1731 (OG) |
20665-Construction / Supervision of new Road Works. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1831.155 | 1226.049 | 25 | 25 | 25 | 25 | 1251.049 | 580.106 | 68% |
68% May - 2021 |
Construction supervision of new road works.
feasilbility study and design of 305 Km provincial roads. |
No Image |
1732 (OG) |
20675-F/S and Design of Projects of Various Roads. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 630 | 278.496 | 25 | 25 | 25 | 25 | 303.496 | 326.504 | 48% |
48% May - 2021 |
PC-II for Rs.30 m approved on 16/03/2021. Work start |
No Image |
1733 (OG) |
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5- Stations. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 498.16 | 194.713 | 25 | 25 | 25 | 25 | 219.713 | 278.447 | 44% |
44% May - 2021 |
8 weight station as per revised PC-I. Work in progress.
Package I 25%
Package II 40%
Package III 70% |
No Image |
Package-1 (02 Nos of weight stations)
i. Timergara, Munda, Khar, Ghallani, Pirqalla, Peshawar at peshawar at Pirqalla (S-$
ii. Shahbazgara, Rustam, Ambella, Daggar, Karakar, Barikot road at Baba Serai
Package-2 (03 Nos of weight stations)
i. Kohat, Hungu, Thall, Parachinar
ii. Tajakzai, Lakki, Daratang Chashma Chowk
iii. Thall Mirali, Isha Razmak, Khirgi Tank, D.I Khan (Darya Khan)
Package-3 (03 Nos of weight stations)
i. Weight Station at Eastern Bypass Mardan (Eastern)
ii. Eastern Bypass Mardan at Entry point (Shifted to Rustum)
iii. Weight Station on (Western) Bypass Mardan Towards Charsdda Road. | |||||||||||||||||||
1734 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 KM), District Kohat and Hangu |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 1647.193 | 100 | 198 | 198 | 198 | 1845.193 | 1012.665 | 63% |
67% May - 2021 |
Total Length: 22.529 KM
Pac-I Aphat: 5.449/5.800) completed
Pac-II Aphat: 5.133/5.750) completed
Pac-III Aphat: 6.00/6.00) completed |
No Image |
Package-1 (Sherkot to UsterzaI Bala) (5.643 - KM)
Package-2 (UsterzaI Bala to Raeesan) (5.626 - KM)
Package-3 (Raeesan to Babar Qilla) (5.628 - KM)
Package-4 (04 Nos Bridges) (5.5.632 - KM) | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 75 | 1780.505 | 1016.261 | 64% |
64% May - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1736 (OG) |
160193-Project Directorate for Swat Expressway. |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.611 | 250 | 74.579 | 74.579 | 74.5785 | 74.579 | 324.579 | 0 | 100% |
100% May - 2021 |
3rd Revised PC-1 Amouting Rs 411 M has been approved by PDWD held on 26/08/20. |
No Image |
1737 (OG) |
180600-F/S, Design and Reconstruction of RCC Bridges i) Pir Bala on KM-7, Peshawar, ii) Kanawer Bridge on Charsadda Tangi Road, iii) Elai Bridge on S-10 at Buner and iv) Bridge on Haripur-Beer Section S-12 (Length-160m) |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 668.596 | 230 | 40 | 40 | 40 | 40 | 270 | 398.596 | 40% |
40% May - 2021 |
04- Pacakges
1- Work order issued , work could not be stated due to paucity of fund.
2- Test Piles completed.
3- Arrangment of pile load test is in progress.
4- Test piles completed.
Working piles 36/52 No completed. Prestressed girders 23/25 Nos completed. |
No Image |
1. RCC Bridge Pir Bala
2. Kaniwar Bridge
3. Elai Kalay Bridge
4. Haripur Beer Road bridge | |||||||||||||||||||
1738 (OG) |
190511-F/S and detailed design of Peshawar - D.I.Khan Motorway.(320 KM). |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 320 | 0 | 10 | 10 | 10 | 10 | 10 | 310 | 3% |
3% May - 2021 |
PC-I amounting to Rs: 276 has been clearted by PDWP & submitted to CDWP. |
No Image |
1739 (OG) |
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km) |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 898.98 | 50 | 50 | 0 | 0 | 0 | 50 | 798.98 | 11% |
6% May - 2021 |
work stopped |
No Image |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
May - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
1741 (New) |
190490-Construction of Flyover at Kulader Chowk Charsadda. |
Charsadda PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 920.92 | 0 | 25 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II approved. Design finalized with consultant on 11/11/2020. PC-I under preparation
Summary submitted for Change of Site |
No Image |
1742 (New) |
190558-Dualization of Swabi Jehangira Road left over portion 11 Km i/c bridge on River Indus |
Swabi PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3367.708 | 0 | 50 | 50 | 50 | 50 | 50 | 3317.708 | 1% |
1% May - 2021 |
Tender completed |
No Image |
1743 (New) |
190531-F/S, Detailed Engg and Construction of Swat Expressway from Chakdarra to Fatehpur (Phase-II) (IDA Assisted) |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 20 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Tender has been floated on 22/02/2021
PC-I has been cleared by CDWP AA amounting to Rs. 20 billion has been issued against land acquisation |
No Image |
1744 (New) |
200321-F/S and Construction of Kandian Valley - Kalam Road, Upper Kohistan. |
Kohistan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 5 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II approved for Rs-5.00 M in 2/10/2020 PDWP |
No Image |
1745 (New) |
190556-F/S, Design & Reconst: of Bridges: Arsala(S-11), Aghan Pur(S-10), Drwaza Kas(S-8), Doghi (S-12), Bada on Swabi Topi Rd(S-1), Khyali(S-1), Matra (S-4), Machni (S-4), kababian (S-4), Dehri (S-10), Aloch Puran(S-10A), Chena on Swari Ambela Rd (S-10A) |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1990.727 | 0 | 50 | 50 | 50 | 50 | 50 | 1940.727 | 3% |
3% May - 2021 |
Procurement is under process. |
No Image |
1. Aghan Pur Bridge Rustam Abella
2. Aloch Bridge Buner
3. Chena Bridge Buner
4. Gwaleraia Bridge Fazal Banda ROad
5. Drwaza Kas Bridge BN ROad
6. Doghi Bridge Oghi Darband ROad | |||||||||||||||||||
1746 (OG) |
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted). |
Provincial PMU |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 75.172 | 24.828 | 34.13 | 34.13 | 6.211 | 81.383 | 0 | 100% |
81% May - 2021 |
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km.
Completion : June-2021. |
No Image |
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 0 | 0 | 0 | 0 | 0 | 0 | 114.982 | - |
- May - 2021 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel | |||||||||||||||||||
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 0 | 0 | 0 | 0 | 0 | 0 | 48.69 | - |
- May - 2021 |
Completed. |
No Image |
Construction of RCC Bridge on Nandehar Khawar | |||||||||||||||||||
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 0 | 10 | 10 | 10 | 8.198 | 8.198 | 90.651 | 10% |
8% May - 2021 |
Completed. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60 | |||||||||||||||||||
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 0 | 0 | 0 | 0 | 0 | 0 | 116.283 | - |
- May - 2021 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah | |||||||||||||||||||
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 332.689 | 0 | 0 | 0 | 0 | 332.689 | 16.431 | - |
95% May - 2021 |
5/6 bridges completed, 1 in progress (Mayar bridge) & village Shamat pur. |
No Image |
| |||||||||||||||||||
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 918.425 | 732.415 | 10 | 10 | 10 | 0 | 732.415 | 176.01 | 81% |
80% May - 2021 |
12 Bridges completed. 1 bridge structure completed |
No Image |
1747 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
PS |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 5 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1748 (OG) |
110388-Constn: of Abutments and Launching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 764 | 221.227 | 10 | 10 | 10 | 0 | 221.227 | 0 | - |
- May - 2021 |
No Image | |
1748 (OG) |
110388-Constn: of Abutments and Launching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted). |
PS |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 10 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1748 (OG) |
110388-Constn: of Abutments and Launching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted). |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.45 | 0 | 0 | 0 | 0 | 0 | 0 | 174.45 | - |
- May - 2021 |
Out of 7 bridges, 6 completed, 1 Pak Army requested for launching of steel bridge. |
No Image |
1) Mula Baba Bridge PK-80
2) Amankot (Rahim Abad) Bridge
3 Rahim Abd Bridge
4 Barikot (Babaji Baba Bridge)
5 Faiz Abad Bridge
6 Kuz Kalay Khwaza Khela by pass bridge
7 chinkolai Faqira Bride
| |||||||||||||||||||
1748 (OG) |
110388-Constn: of Abutments and Launching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted). |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.825 | 0 | 0 | 0 | 0 | 0 | 0 | 67.825 | - |
- May - 2021 |
Completed. |
No Image |
1) Shah Alam bridge (180 feet) | |||||||||||||||||||
1749 (OG) |
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 10.27 | 10 | 10 | 10 | 0 | 10.27 | 0 | - |
- May - 2021 |
PC-II approved. |
No Image |
1750 (OG) |
130510-Feasibiilty Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 7.473 | 10 | 10 | 10 | 0 | 7.473 | 0 | - |
- May - 2021 |
PC-II approved. |
No Image |
1751 (OG) |
130574-Impt/ Rehabilitation & Upgradation of 300 KM roads in Khyber Pakhtunkhwa |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 451.062 | 380.305 | 10 | 10 | 10 | 9.314 | 389.619 | 60.757 | 87% |
86% May - 2021 |
Length 49 Km (85 units) - work in progress. |
No Image |
| |||||||||||||||||||
1751 (OG) |
130574-Impt/ Rehabilitation & Upgradation of 300 KM roads in Khyber Pakhtunkhwa |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 0 | 1.03 | 1.03 | 1.03 | 1.03 | 1.03 | 73.97 | 1% |
1% May - 2021 |
Completed (8.5 Km). |
No Image |
| |||||||||||||||||||
1751 (OG) |
130574-Impt/ Rehabilitation & Upgradation of 300 KM roads in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- May - 2021 |
Completed. |
No Image |
1751 (OG) |
130574-Impt/ Rehabilitation & Upgradation of 300 KM roads in Khyber Pakhtunkhwa |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.9 | 0 | 0 | 0 | 0 | 0 | 0 | 61.9 | - |
- May - 2021 |
Completed (7 Km). |
No Image |
| |||||||||||||||||||
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 |