1047
(OG)
191147-180207 - Construction/Rehab of existing Levies Picquets and barracks in District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 31.769 12.057 18.405 15.363 15.363 5.724 17.781 1.307 96% 56%
May - 2021
07 - Units 1. Finishing 2. Land not avaible 3. H/O 4. Finishing 5. H/O 6. Finishing 7. H/O
No Image
1 Levy Picquet at Top Mandai
2 Levy Picquet at Asil Targhaow
3 Levy Picquet at Line Civil Colony
4 Levy Picquet at Darbano
5 Levy Picquet at DHQ Hospital Khar
6 Levy Picquet at Civil Colony Khar
7 Levy Picquet at Hopistal Khar
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 67.107 47.786 1.6 1.6 1.6 1.6 49.386 17.721 74% 74%
May - 2021
05- Units 1. Finishing 2. Finishing 3. Land not avaible 4. H/O 5. H/O
No Image
1 Levies Barrak in Civil Colony Qazafi
2 Nawagai
3 Maronshah
4 Area Tulam Khel
5 Shahnarai Dag Khar
 
Scope of work:
  • Levis Barracks 64 pesons
  • Levy Piquet
 
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 18.309 19.767 1.232 1.232 1.232 0.973 20.74 0 100% 100%
May - 2021
05- Units 02 units - Completed. 03 units - Finishing in progress.
No Image
1 Levy Barrak at Shalghazi Daryoba
2 Levy Barrak at  Bizan Khel
3 Check Post at Janday Utmanzai
4 Check Post at Stara
5 02 Nos Check Points at Shalgazai
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 2.2 2.4 0 0 0 0 2.4 0 - 100%
May - 2021
Completed
No Image
Lockup at Shamshato Rest
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 5.459 5.414 0.045 0.045 0.045 0 5.414 0 100% 99%
May - 2021
Completed
No Image
Const: of Levy Picqut near Pir Badshah Kot Ping
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 32.597 9.919 0 0 0 0 9.919 22.678 - 30%
May - 2021
06- Units 05 Nos work in progress, unite at S.No 6 work could not be started due to dispute.
No Image
1 Const: of Levy Post/Picquet
I Shaheed Manzay, Aka Khel Bara
ii Gulmast Killi Shalobar Qamber Khel Bara
iii Kohi Chowk, Malikdin, Khel Area
iv Nogzai Baba Shalobar Bara
v Const: of Levy Picquet at Secretary Pull
vi Bara Bazar Near Shlobar Qamber Khel Chwok
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 13.765 8.394 1.191 1.191 1.191 0.67 9.064 4.18 70% 66%
May - 2021
03- Units - all in progress. 1 B/wall in progress 2 B/wall in progress 3 Finishing
No Image
1 Lecy Picquet at Ali Rehaman Seraj Khan Queata Khwa  (TS 5.218)
2 Levy Picquet at Hussain Khel (TS 5.218)
3 Levy Barrak at Tajori
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 55.731 22.781 1.587 1.587 1.587 1.252 24.033 31.363 44% 43%
May - 2021
15- Units work in progress.
No Image
1 Levy Picquet at  Dab Ambar
2 Levy Picquet at Khari Darra
3 Levy Picquet at Bhatto Meina Ambar
4 Levy Picquet at Shatee Meina Amber
5 Levy Picquet at Garang
6 Levy Picquet at Bedmannai Kandao
7 Levy Picquet at Bedmanani Bia Area
8 Levy Picquet at Gursai Road
9 Levy Picquet at Qalagai Kandao
10 02 rooms at Tiyab Road S/T Latee Camp Piquet
11 02 rooms at Mian Mandai S/T Tehsil Building Tehsil PIndiali
12 02 rooms at Babi Khel Post S/T Umer Banda Tehsil Ekka Ghund
13 02 rooms at Raziq post
14 02 rooms at Ghursal Border
15 02 rooms at Chanda Top S/T Sagi Tehisl Safi
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 70.16 46.939 3.191 3.191 3.191 3.191 50.13 20.03 71% 71%
May - 2021
09- Units . 4 - Units upto roof level. 4 Units in finishing stage, 1 unit up to DPC level.
No Image
1 Lookup at Mirn shah
2 Khazan Picquet
3 Maddi Khel
4 Bobali
5 Shamiri Aba Khel
6 Katria Khusali No I
7 Katria Khusali No II
8 Jalir Zakir Khel
9 Khaisoor
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 396.548 3.691 0.3 0.3 0.3 0 3.691 392.557 1% 1%
May - 2021
Luck ups : Flooring Barraks not started. Gurard room no started. Group rapir not started. .
No Image
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 396.548 141.251 20 20 0 0 141.251 0 - -
May - 2021
No Image
1048
(OG)
191179-170342-Construction and Rehabilitation of Levy Barraks, Levy Picquets and Lockups in All Agencies /FRs. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 52.968 10.505 0 0 0 0 10.505 42.463 - 20%
May - 2021
0- Units . Completed =1 In progress =9
No Image
1 Levy picquet Saraogha
2 Levy picquet Spinkari
3 Levy picquet Nano
4 Levy picquet Upper Madi Jan
5 Levy picquet Karama
6 Levy picquet Servek
7 Levy picquet Barwan
8 Levy picquet Chaghmalali
9 Levy picquet Zirarat
10 Levy picquet Khamrang Bridge
1049
(OG)
191587-100205-Establishment of Levy Trainning Center at Shah Kass, Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 173.12 112.886 0 0 0 0 112.886 0 - -
May - 2021
No Image
1050
(OG)
191157-180544 - Construction / Reconstruction and Rehabilitation of Levy / Khassadar Picquets in Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 46.849 28.767 43.174 43.174 25.133 8.024 36.791 0 100% 79%
May - 2021
11- Components Completed=1 In progress =10
No Image
  1. Levy/Khasadar Barracks Mamak Khel Shuza Khula
  2. Levy/Khasadar Barracks Kasi Comp:
  3.  Sobo Mela Ping 
  4. Levy/Khasadar Barracks Khecaha Moar
  5. Levy/Khasadar Barracks  Kazzoki
  6. Levy/Khasadar Barracks Perveez Khel
  7. Levy/Khasadar Barracks Shuza / Pirtangi
  8. Levy/Khasadar Barracks Head Zam (Soberdar Ibrahim)
  9.  Picquet Tangi 
  10. Levy/Khasadar Barracks Near Alquraish Khrigi
  11. Levy/Khasadar Barracks Bazi Arzikhel
1051
(OG)
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 57.036 30.877 34.158 28.528 28.528 22.884 53.761 0 100% 94%
May - 2021
12- Components 05 Units - H/O 02 Units - Completed 05 Units - Work in progress
No Image
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12  Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2
1052
(OG)
191117-170217-Construction / Reconstruction and Rehabilitation of Khassadar / Levy Picquets at FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 14.571 4.273 10.298 8.858 8.858 1.274 5.547 0 100% 38%
May - 2021
03- Units S.No 2 in Progress, and S.No 1,3 dispute, letter to AC Darra Adam Khel for solution of dispute on 06/01/20.
No Image
1 Sunni Khel
2 Babazai Chowk
3 Toor Chappar
4 Solorziation of Sunni Khel
5 Solorzaition of  Babzai Chowk
6 Solozation of Toor Chappar
1053
(OG)
191139-180464 - Construction of Small Levy/Khassadar Head quarter at Paya Jawaki Sub-Division Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 17 0 17 10.495 10.495 0 0 0 100% -
May - 2021
Approved
No Image
1054
(OG)
191140-180465 - Construction of Boundary Wall and Solarization of Existing Levis/Khasadar Piquets in Sub-Division Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 15.603 0 15.603 12.633 12.633 7.22 7.22 0 100% 46%
May - 2021
03 Units 1 Completed 2 B/Wall Completed 3 B/Wall Completed
No Image
1 Piquet Paya Jawaki Sheen Dhand
2 Piquet Paya Jawaki Ibrahim Khel
3 Piquet Paya Jawaki Jammu
 
1055
(OG)
191118-170200-Construction / Reconstruction and Rehabilitation of Levy Check Posts / Piquets in FR Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 26.06 9.183001 16.877 13.419 13.419 0.726 9.909001 0 100% 38%
May - 2021
Work in progress . Letter sent AC Hassan Khel for clearing of 03-Nos sites or execution vide letter No. 07/01/20.
No Image
1 Levy Picquet at  Ghakai Sar Mussa Dara
2 Levy Picquet at Pastawani Top
3 Levy Picquet at Pkhai Bala (Asho Khel)
4 Levy Picquet at Mir Samad Killi
5 Levy Picquet at Ali Khel (Asho Khel)
6 B.wakk of Picquet near Faqir Abad
7 Solarization at Pastawani Top
8 Solarization at Pahai Bala (Asho Khel)
9 Solarization at Shaki Sar Mussa Dara
10 Solarization at Mir Samad Killi
11 Solarization at Ali Khel
1056
(OG)
195240-Extension of Prosecution Services in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 126.704 10 0 0 0 0 10 0 - -
May - 2021
No Image
1057
(OG)
195241-Extension of Parole and Probation Services in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 47.125 0 0 0 0 0 0 0 - -
May - 2021
No Image
1058
(OG)
195238-F/S & Construction of Police Stations and Police Posts including Levies transformations (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 7191.99 0 200 200 0 0 0 0 - -
May - 2021
No Image
1059
(OG)
195239-Training Programs for Police and Levies along with necessary equipments (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1267.727 160 0 0 0 0 160 0 - -
May - 2021
No Image
1060
(New)
200083-F/S for Police Lines in Merged Districts (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
No Image
1060
(New)
200083-F/S for Police Lines in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 20 20 0 0 0 0 - -
May - 2021
No Image
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
Bajaur
30-11--1 30-11--1 - 30-11--1 - 88.837 0 30 30 30 24.239 0 0
May - 2021
02- Units 1. Plaster in progress 2. Plaster in progress
No Image
1 Reha: of Sub Jail Khar
2 Reha: of Sub Jail Nawagi
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
Kurram
30-11--1 30-11--1 - 30-11--1 - 57.629 0 14.961 14.961 14.961 0 0 0
May - 2021
01- Unit Tube well Completd & Rehab: in progress, Type-III Residence Finishing
No Image
1) Sub Jail Para Chinar
 
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 - 28.075 0 14.035 14.035 14.035 0 0 14.04 50% -
May - 2021
02 Units 1 Main building upto DPC level 2 Site not handed over
No Image
1 Sub Jail at Ghallanai
2 Sub Jail at Ekkaghund
 
Scope of work:
  • Main Building
  • B/Wall
  • Dev: work
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 21.939 0 8 8 8 0 0 0
May - 2021
site recently identified
No Image
Lookup at Mir Ali NWA
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
Orakzai
30-11--1 30-11--1 - 30-11--1 - 24.948 0 5 5 5 2.176 2.176 19.948 20% 9%
May - 2021
02 units - all in progress
No Image
1 Sub Jail Head Quarter Baber Mela
2 Sub Jail Kalaya
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 817.59 60 300 300 0 0 60 0 - -
May - 2021
No Image
1061
(OG)
195237-Improvement of existing Political lockups (Sub Jails) and providing Arms & Ammunitions along with other necessary equipments (AIP)
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 34.116 0 10 10 10 6.571 6.571 24.116 29% 19%
May - 2021
02- Components work order issued.
No Image
1062
(New)
200088-F/S for Construction of District Jails in Merged Districts (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
No Image
1062
(New)
200088-F/S for Construction of District Jails in Merged Districts (AIP)
Orakzai
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
No Image
1062
(New)
200088-F/S for Construction of District Jails in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 20 20 0 0 0 0 - -
May - 2021
No Image
1069
(OG)
150772-Cost of Incentives for the Economic Zones Development
Provincial
30-11--1 30-11--1 - 30-11--1 - 2000 912.118 0 0 0 0 912.118 0 - -
May - 2021
No Image
1070
(OG)
190184-Access Road to Rashakai Special Economic Zone
Provincial
30-11--1 30-11--1 - 30-11--1 - 539.713 250 289.713 289.713 0 0 250 0 - -
May - 2021
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
May - 2021
No Image
1072
(OG)
130367-Establishment of Khyber Pakhtunkhwa University of Technology at Nowshera (Phase-I)
Nowshera
30-11--1 30-11--1 - 30-11--1 - 2799.676 744.2 0 0 0 0 744.2 0 - -
May - 2021
No Image
1073
(OG)
110536-Economic Revitalization in Khyber Pakhtunkhwa. (ERKP) FEC = Rs. 6227.237 Million.
Provincial
30-11--1 30-11--1 - 30-11--1 - 51.05 34.952 0 0 0 0 34.952 0 - -
May - 2021
No Image
1074
(New)
200054-Economic Growth & jobs Creation through Tecnical/Financial Assistance(ERKF Model)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3625 0 0 0 0 0 0 0 - -
May - 2021
No Image
1075
(New)
200300-Establishment of Oxygen Plant.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 10 10 0 0 0 0 - -
May - 2021
No Image
1076
(OG)
190198-Establishment of SIE Peshawar-2 (Purchase of land)
Peshawar
30-11--1 30-11--1 - 30-11--1 - 443.354 43 0 0 0 0 43 0 - -
May - 2021
No Image
1077
(OG)
150370-Acquisition of Land and Establishment of Small Industrial Estate at Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 105.616 105.615 0.001 0.001 0 0 105.615 0 - -
May - 2021
No Image
1078
(OG)
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 130 77 0 0 0 0 77 0 - -
May - 2021
No Image
1079
(OG)
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra).
Provincial
30-11--1 30-11--1 - 30-11--1 - 322.671 271.671 0 0 0 0 271.671 0 - -
May - 2021
No Image
1080
(OG)
160113-KP Women Skill & Entrepreneurship Development Programme (KP WSEDPP) & Readymade Garments Industry.
Provincial
30-11--1 30-11--1 - 30-11--1 - 140.278 94.99001 0 0 0 0 94.99001 0 - -
May - 2021
No Image
1081
(OG)
180485-Provision of Independent Electric Feeders at SIEs Peshawar & Mardan
Provincial
30-11--1 30-11--1 - 30-11--1 - 71.846 45 0 0 0 0 45 0 - -
May - 2021
No Image
1082
(New)
190204-Provision of Independent Electric Feeder at SIE Khalabat
Swabi
30-11--1 30-11--1 - 30-11--1 Line Deptt 60 0 0 0 0 0 0 0 - -
May - 2021
No Image
1083
(New)
190199-Acquisition of land for expansion of SIEs Karak & Bannu
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 0 0 0 0 0 0 - -