Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : May - 2021,

Showing Page Number : 32 of 69

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
971
(OG)
191580-170440 - Establishment of Govt Degree College Barang in Bajaur (GD) . [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 160.412 63.688 102.724 69.109 69.109 62.815 126.503 0 100% 79%
May - 2021
M/B Finihsing 50 Student Hostel Finihsing 01 Teacher Hostel in porgress 01 Indoor Hall Roof Laid Demand 10 M
No Image
Establishment of Govt Degree College Barang in Bajaur
 
Scope of work:
  • Academic Block
  • C/Rooms 14 Nos
  • Science lab
  • Computer Lab
  • Office Block
  • Multi Purpose Hall
  • Cat-III 01 Nos
  • Cat-IV 02 Nos
  • Type III Residence: 02 Nos
  • Type IV Residence: 02 Nos
  • Dev: work
972
(OG)
191569-140360 - Establishment of PMU for Establishment of FATA University. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 66 40.008 0 0 0 0 40.008 0 - -
May - 2021
No Image
973
(OG)
191571-160434 - Completion of Balance Work of Govt.Girls Degree College Dara Adam Khel, FR Kohat. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 99.702 64.644 35.058 35.058 0 0 64.644 0 - -
May - 2021
No Image
974
(OG)
191578-160459 - Award of In Land Scholarships to FATA Students During (2017-18) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 350 150 0 0 0 0 150 0 - -
May - 2021
No Image
975
(OG)
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 198.551 14.137 190.505 64.712 64.712 2.447 16.584 0 100% 8%
May - 2021
C/Wall completed. Test Bare in progress. Levelling, Dressing in progress. Cannot be completed due to revision Revised DCE submitted
No Image
Construction of Building for Govt Degree College Ara Khel, FR Kohat.
976
(OG)
191570-150292 - Completion of Balance Work of "Upgradation of GHSS Sama Badabera to Degree College" in FR Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 54.544 26.959 17.944 14.56 14.56 11.594 38.553 9.641 82% 71%
May - 2021
Acadmic block finishing, B/Wall, Examination Hall plaster completed. Cafereria flooring in progress. Demand Rs: 10 M
No Image
1 GHSS Sama Badaber to Degree College FR Peshawar
977
(OG)
191572-970106 - Conversion of 1 Public School into Establishment of GGDC in FR Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 52.177 47.996 4.583 4.583 4.583 0 47.996 0 100% 92%
May - 2021
01- Units Old work in finishing stage. Finishing in progress. Plastering flooring in progress.
No Image
1 GGDC In FR Peshawar
2 Work internal Electrificaiton
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 22 0 16 16 16 3.793 3.793 6 73% 17%
May - 2021
Work started
No Image
GDC Kotka Habibullah Wazir
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 38 0 15 15 15 7 7 23 39% 18%
May - 2021
Repair work 90% Completed B/Wall and watch poere in progress
No Image
GDC Jandola.
GGDC Jandola.
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 - 131 0 29.104 29.104 29.104 27.831 27.831 101.896 22% 21%
May - 2021
6- Units all in progress
No Image
1 GGDC Jamrud
2 GDC Jamrud Khyber
3 GDC Kohi Sher Hiader Khyber
4 GPGC Landi Kotal Khyber
5 GCMS Jamrud Khyber
6  Solarizaton
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
Kurram
30-11--1 30-11--1 - 30-11--1 - 237.73 0 106.316 106.316 106.316 106.316 106.316 131.414 45% 45%
May - 2021
04- Units 1. Rehab: in progress 2. Rehab: in progress 3. Rehab: in progress 4. Rehab: in progress
No Image
1 GGDC No.1 Parachinar
2 GPGC Parachinar
3 GGDC No.2 Parachinar
4 GCMS Parachinar
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 - 145.363 0 43 43 43 20.349 20.349 102.363 30% 14%
May - 2021
04 Units- 1. M/Buld: upto roof level 2. Roof laid 3. Roof treatement 4. Distempring in progress
No Image
1 GDC Lakaro
2 GGDC Ekka Ghund
3 GDC Ekka Ghund
4 GCMS at Ghallanai
 
Scope of work:
  • M/ Building
  • Studen Hostel
  • Renvoation of Exam Hall
  • Solar System
  • Int: Elec: & W/S
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 60 0 19 19 19 14.087 14.087 41 32% 23%
May - 2021
3- Units. 1 Admin Block upto DPC 2 80% Completed 3 70% Completed
No Image
1 GDC Mirali? Rs: 15.00 M
2 GPGC Miranshah? Rs: 30.00 M
3 GCMS Miranshah? Rs: 15.00 M
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
Orakzai
30-11--1 30-11--1 - 30-11--1 - 30 0 16 16 16 6.795 6.795 14 53% 23%
May - 2021
02 Uinits 1 50% C/Wall Completed 2 Super Strucutre in progress
No Image
GGDC Kalaya ? Rs; 15.00 M
GC Ghiljo ? Rs; 15.00 M
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1109.79 0 500 500 0 0 0 0 - -
May - 2021
No Image
978
(OG)
195132-Strengthening and rehabilitation of existing colleges (General + Commerce) (AIP)
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 40 0 0 0 0 0 0 40 - -
May - 2021
2- Components. Procurement under process.
No Image
 
979
(OG)
195134-Provision of Transport Facilities to Higher Educational Institutes (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 945 450 0 0 0 0 450 0 - -
May - 2021
No Image
980
(New)
195133-Strengthening of BS Programme (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 0 0 0 0 0 0 - -
May - 2021
No Image
981
(New)
195136-Performance based package for the teaching faculty (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1899 0 0 0 0 0 0 0 - -
May - 2021
No Image
982
(New)
195137-Capacity building programme for college faculty (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2800 0 0 0 0 0 0 0 - -
May - 2021
No Image
983
(New)
195138-Provision of staff to existing colleges (Commerce + General) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1728 0 0 0 0 0 0 0 - -
May - 2021
No Image
984
(New)
200119-Provision of Land and Construction of Building for exsiting Government Colleges in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 100 100 0 0 0 0 - -
May - 2021
No Image
985
(New)
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP)
Bajaur
30-11--1 30-11--1 - 30-11--1 Line Deptt 230 0 100 0 0 0 0 130 43% -
May - 2021
Scope of work awaited. DDWP held on 29-03-21 AA. Awiated
No Image
1 GPGC Khar
2 GDC Nawagai
3 GCMS Khar
985
(New)
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP)
FR Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 100 0 0 0 0 50 67% -
May - 2021
Scope of work awaited. DDWP held on 29-03-21 AA. Awiated
No Image
1. GDC Jandola
2. GGDC Jandola
985
(New)
200120-Provision of Additonal Academic Infrstructure & Missing Facilities in the existing Government Colleges in Merged Areas on need basis (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1700 0 100 100 0 0 0 0 - -
May - 2021
No Image
986
(New)
191583-Introduction of BS Program in Colleges in all Tribal Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 0 0 0 0 0 0 - -
May - 2021
No Image
987
(New)
195127-Provision of Stipends and scholarships for students of Merged Areas (AIP).
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1700 0 0 0 0 0 0 0 - -
May - 2021
No Image
988
(OG)
195311-Feasibility Study for the Establishment of Education City at Barwand Mehsud Area in SW (AIP)
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 42.59 0 0 0 0 0 0 0 - -
May - 2021
No Image
989
(OG)
195140-Feasibility for the establishment of University in NW (AIP).
Provincial
30-11--1 30-11--1 - 30-11--1 - 15 0 0 0 0 0 0 0 - -
May - 2021
No Image
990
(New)
191585-F/S & Establishment/Upgradition of Colleges/Universities/Campuses in Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 0 0 0 0 0 0 - -
May - 2021
No Image
991
(OG)
180093-Reformation & Skills Development facilities for Probationers(Rule of Law Road map)
Provincial
30-11--1 30-11--1 - 30-11--1 - 76.297 10 0 0 0 0 10 0 - -
May - 2021
No Image
992
(OG)
180104-Case Management System in the Directorate of Prosecution and its District Offices (Rule of Law Road map)
Provincial
30-11--1 30-11--1 - 30-11--1 - 94.927 0 0 0 0 0 0 0 - -
May - 2021
No Image
993
(OG)
180518-Computerization of Arms Licenses in the remaining Districts of khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 - 50.976 0 0 0 0 0 0 0 - -
May - 2021
No Image
994
(New)
170331-Establishment of Forensic Science Laboratory (FSL) at Peshawar (UNDP Assisted).
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
May - 2021
No Image
995
(New)
160435-Strengthening Rule of Law Project (SRLP) (UNDP Assisted). PDWP cleared on 31-01-2018.
Provincial
30-11--1 30-11--1 - 30-11--1 - 200 0 0 0 0 0 0 0 - -
May - 2021
No Image
996
(New)
200089-Establishment & Strengthening of Civilian oversight Bodies under Khyber Pakhtunkhwa Police Act, 2017.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 100 0 0 0 0 0 0 0 - -
May - 2021
No Image
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
May - 2021
No Image
998
(OG)
20602-Construction of Central Police Office in Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 658.831 0 100 71 71 67.851 0 0
May - 2021
Finishing in progress.
No Image
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy)
999
(OG)
140150-Establishment of Project Management Unit (PMU) for Safe City Project Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 142.608 75 0 0 0 0 75 0 - -
May - 2021
No Image
1000
(OG)
140263-F/S & Construction of Headquarters for Counter Terrorism Department at District Peshawar(Ternab)
Peshawar
30-11--1 30-11--1 - 30-11--1 - 231.573 148 58.574 58.574 0 0 148 0 - -
May - 2021
No Image
1001
(OG)
150636-Construction of Watch Towers in Cantonment & Rural Division for Enhanced Security in Funnel Area of Bacha Khan International Airport Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 172.521 162.337 10.184 10.184 0 0 162.337 0 - -
May - 2021
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
May - 2021
Approved.
No Image
1003
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0 0 0 0 0 0 - -
May - 2021
No Image
1004
(OG)
200033-Acquisition of Land for Heavy Firing Range adjacent to Elite Police Training Center, Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 - 203 0 30.611 30.611 0 0 0 0 - -
May - 2021
No Image
1005
(OG)
200034-Purchase of Land for Construction of Police Line Daggar, Buner
Buner
30-11--1 30-11--1 - 30-11--1 - 46.31 0 46.31 46.31 0 0 0 0 - -
May - 2021
No Image
1006
(OG)
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower),
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 70 67.66 2.34 2.34 0 0 67.66 0 - -
May - 2021
No Image
1007
(OG)
120248-Special Development Support for Khyber Pakhtunkhwa Police (Tor Ghar = Rs. 400.00 M Phase-III)
Provincial
30-11--1 30-11--1 - 30-11--1 - 2000 1331.053 100 100 0 0 1331.053 0 - -
May - 2021
No Image
1008
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 627.013 110 110 0 0 627.013 0 - -
May - 2021
No Image
1009
(OG)
140124-Special Development Support for Khyber Pakhtunkhwa Police and Creation of Model Police Stations (SDSP-V).
Provincial
30-11--1 30-11--1 - 30-11--1 - 71.735 149.923 5 5 0 0 149.923 0 100% 100%
May - 2021
Approved.
No Image
1010
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 180 139.934 40.066 40.066 0 0 139.934 0 - -
May - 2021
No Image
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69