Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : May - 2021,

Showing Page Number : 31 of 69

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
924
(New)
200307-F/S for Establishment of Commerce College at Nowshera
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 0 0 0 0 0 0 - -
May - 2021
F/S executed by client Deptt themselves
No Image
925
(New)
200308-F/S for Establishment of Girls Commerce College at Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 0 0 0 0 0 0 - -
May - 2021
No Image
926
(New)
200305-F/S for Giving the full fledged university to the existing campus of Abdul Wali Khan University (Dir Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 0 0 0 0 0 0 - -
May - 2021
No Image
927
(New)
200118-Provision of water supply/Filtration Plants to Govt Colleges of Khyber Pakhtunkihawa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 200 0 0 0 0 0 0 0 - -
May - 2021
No Image
928
(New)
200137-Purchase of Necessary Items (Furniture, Equipment, Plant & Machinery, Sport Goods, Computer & Allied Accessories, etc.) for Colleges on Need Basis.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 550 0 0 0 0 0 0 0 - -
May - 2021
No Image
929
(New)
200138-Provision of Addtioanl infrastructure and repair of exsiting colleges
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 Line Deptt 38 0 0 0 0 0 0 38 - -
May - 2021
05- Unit 1. 70% Completed 2. 3. Dispute 4. 5. Solar System/Pressure pump in progress
No Image
  1. GGDC Sarai Naurang
  2. GDC Sarai Naurang
  3. GDC Tajori
  4. GPGC Lakki Marwat
  5. GDC Issak Khel
929
(New)
200138-Provision of Addtioanl infrastructure and repair of exsiting colleges
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1500 0 300 300 0 0 0 0 - -
May - 2021
No Image
930
(New)
200303-F/S for Establishment of 20 Govt Degree Colleges in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
Approved for consultant on08/10/2020.
No Image
930
(New)
200303-F/S for Establishment of 20 Govt Degree Colleges in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 0 0 0 0 0 0 - -
May - 2021
No Image
931
(New)
200306-F/S for Provision of Transport facilities for colleges
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 10 0 0 0 0 0 0 0 - -
May - 2021
No Image
932
(OG)
150052-Re-Construction of Building for GCMS(Boys), D.I Khan
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 224.291 161.145 53.36 37.165 37.165 36.165 197.31 9.786 96% 88%
May - 2021
01- Unit Completed and occupied by College administration PC-IV yet not by HED.
No Image
GCMS Boys DI.Khan
 
Scope of work:
  • Admn: Block
  • Academic Block
  • Gurad Room
  • Dev: Work
933
(OG)
100367-Construction of Building for Commerce College near GPI at Karak.
Karak
30-11--1 30-11--1 - 30-11--1 - 313.019 265.78 47.239 29 29 19.316 285.096 0 100% 91%
May - 2021
Main building - Finishing in progress. GF finishin in progress. Student Hostel:- joinery in progress. Principal Residence:- finishing in progress. Bus Garages- Layout given. Demand Rs. 10 M
No Image
Karak
934
(OG)
150108-Establishment of GCMS Women Sawbi
Swabi
30-11--1 30-11--1 - 30-11--1 - 220.58 199.516 38.46 24 24 19 218.516 0 100% 99%
May - 2021
a. Main Bldg: = Finishing in progress. b. B/Wall completed . c. Academy Block = I & II = Finishing in progress. d. Administration Block = Finishing in progress. e. Finishing in progress PC-IV submitted
No Image
GCMS Women Swabi
935
(OG)
180234-Provision of Furniture & Equipments etc at GCMS Mansehra
Mansehra
30-11--1 30-11--1 - 30-11--1 - 14.985 14.98 0 0 0 0 14.98 0 - -
May - 2021
No Image
936
(OG)
140859-Re-construction of Building of GCMS (Boys) Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 231.514 189.21 56.011 56.011 56.011 44.011 233.221 0 100% 100%
May - 2021
01- Unit Finishing in progress
No Image
GCMS (Boys) Abbottabad.
 
Scope of work:
  • Academic Block
  • Admin Block
  • Suits 02 Nos
  • Exam Hall
937
(OG)
180527-Feasibilty Study/ Plan for Introduction/ Establishment of Tourism & Hotel Mangament Centres (exploring PPP mode).
Provincial
30-11--1 30-11--1 - 30-11--1 - 10 2.5 0 0 0 0 2.5 0 - -
May - 2021
No Image
938
(OG)
140616-Strengthening of Planning Cell of Higher Education Department (Phase-II)
Provincial
30-11--1 30-11--1 - 30-11--1 - 72.18 36.55 0 0 0 0 36.55 0 - -
May - 2021
No Image
939
(OG)
170009-Strengthening of BS Program and teacher engagement for BS-4 years degree programme.
Provincial
30-11--1 30-11--1 - 30-11--1 - 2619.5 1154.68 0 0 0 0 1154.68 0 - -
May - 2021
No Image
940
(OG)
170035-Quality Assurance Programme.
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 204.431 0 0 0 0 0 0 204.431 - -
May - 2021
Procurement under process.
No Image
940
(OG)
170035-Quality Assurance Programme
Provincial
30-11--1 30-11--1 - 30-11--1 - 97.579 26.45 0 0 0 0 26.45 0 - -
May - 2021
No Image
941
(OG)
180530-Strengthening of HEMIS Cell
Provincial
30-11--1 30-11--1 - 30-11--1 - 28 2.5 0 0 0 0 2.5 0 - -
May - 2021
No Image
942
(New)
200117-Mandatory Training Program for college Teachers (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 100 0 0 0 0 0 0 0 - -
May - 2021
No Image
943
(OG)
180246-Up-gradation of University of Science & Technology Bannu sub campus Lakki Marwat to a full fledged University
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 238 217.999 0 0 0 0 217.999 0 - -
May - 2021
No Image
944
(OG)
170032-Support to SBBU women University Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 188.54 15 0 0 0 0 15 0 - -
May - 2021
No Image
945
(OG)
170561-Support to Islamia College University Peshawar (for Research Center)
Peshawar
30-11--1 30-11--1 - 30-11--1 - 221.984 221.983 0 0 0 0 221.983 0 - -
May - 2021
No Image
946
(OG)
170560-Support to Bacha Khan University Charsadda
Charsadda
30-11--1 30-11--1 - 30-11--1 - 154.36 5 0 0 0 0 5 0 - -
May - 2021
No Image
947
(OG)
130548-Establishment of Women University Campus in Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 1500.758 1215 0 0 0 0 1215 0 - -
May - 2021
No Image
948
(OG)
160567-Construction of Academic Block in GIK Institute of Engineering
Swabi
30-11--1 30-11--1 - 30-11--1 - 999.254 622 0 0 0 0 622 0 - -
May - 2021
No Image
949
(OG)
150045-Establishment of Women University at Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 1739.418 453.75 0 0 0 0 453.75 0 - -
May - 2021
No Image
950
(OG)
180248-F/S and provision for Up-gradation of UET Sub Campus Mardan to the level of University
Mardan
30-11--1 30-11--1 - 30-11--1 - 953.587 305.3 0 0 0 0 305.3 0 - -
May - 2021
No Image
951
(OG)
180247-Provision of Funds for the balance civil works at University of Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 150 20 0 0 0 0 20 0 - -
May - 2021
No Image
952
(OG)
151057-Strengthening of Abdul Wali Khan Campus at Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 130.011 0 0 0 0 130.011 0 - -
May - 2021
No Image
953
(OG)
160568-Up gradation of Abdul Wali Khan Campus at Buner to a full fledge University
Buner
30-11--1 30-11--1 - 30-11--1 - 315.331 215 0 0 0 0 215 0 - -
May - 2021
No Image
954
(OG)
170655-F/S & Construction of building for Buner University District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 55 0 0 0 0 0 0 0 - -
May - 2021
No Image
955
(OG)
130549-Establishment of Swat University (Counterpart funding for PSDP Project)
Swat
30-11--1 30-11--1 - 30-11--1 - 1640.465 1090 0 0 0 0 1090 0 - -
May - 2021
No Image
956
(OG)
150042-Establishment of Sub-Campus of UET at Dir (Upper)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 1129.437 250 0 0 0 0 250 0 - -
May - 2021
No Image
957
(OG)
160570-Upgradtion of existing University Campuses to a full fledge University (including land cost) at Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 402.02 302.091 0 0 0 0 302.091 0 - -
May - 2021
No Image
958
(OG)
170030-Pak Austria Facchochsule institute of Applied Sciences and technology (PAF-IAST)
Haripur
30-11--1 30-11--1 - 30-11--1 - 6301.92 2800 0 0 0 0 2800 0 - -
May - 2021
No Image
959
(OG)
180240-Provision of Access Road & Strengthening of University of Science & Technology Bannu (PC-II approved)
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 18 0 0 0 0 18 0 - -
May - 2021
No Image
960
(OG)
180528-Support to Energy Centre of UET Peshawar ( Donor Assisted)
Provincial
30-11--1 30-11--1 - 30-11--1 - 40 36.25 0 0 0 0 36.25 0 - -
May - 2021
No Image
961
(OG)
180580-Establishment of Pakhtunkhwa Economic Policy Research Institute at AWKUM.
Provincial
30-11--1 30-11--1 - 30-11--1 - 119.28 56.75 0 0 0 0 56.75 0 - -
May - 2021
No Image
962
(OG)
190237- Establishment & Feasibility Study of UET Swat
Provincial
30-11--1 30-11--1 - 30-11--1 - 7000 14.35 100 100 0 0 14.35 0 - -
May - 2021
No Image
963
(New)
190443-Support to Abdul Wali Khan University Mardan for Special Initiatives.
Mardan
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
May - 2021
No Image
964
(New)
200332-F/S of Swat University Campus at Dargai District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
May - 2021
No Image
965
(OG)
191568-070200 - Construction of 2 Hostels (One for Students & One for Teachers) and provision of missing facilities in Govt Degree College Wana, SWA
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 119.95 110.915 8.512 5.398 5.398 0 110.915 0.523 100% 92%
May - 2021
06- Units 1. Completed & H/O 2. Completed & H/O 3. Completed 4. Roof treatment 5. Completed & H/O 6. Completed & H/O
No Image
1 Student Hostel
2 Teacher Hostel
3 06 Nos Add: Class room
4 Studen Cum Teacher Hostel
5 Tow No Type IV Quarter
6 B/T Road
966
(OG)
191574-150165 - Construction of Student Hostels and Residential Quarters for Staff in Govt. Degree College in Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 64.826 38.95 18.876 11.43 11.43 0 38.95 7 89% 60%
May - 2021
04- Units 1. Finishing 2. Roofing 3. Finishing 4. Finishing
No Image
1 Student Hostel
2 Cat: III Residentail 01 No
3 Type IV Quarter 01
4 Type V Quarter 01
967
(OG)
191575-160036 - Re-construction of GDC Ladha, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 162.6 97.691 54.91 27.887 27.887 10.955 108.646 9.999 94% 67%
May - 2021
04- Packages Work in progress on all packages.
No Image
Package 1
Package 2
Package 3
Package 4
968
(OG)
191577-170423 - Reconstruction of Degree College Sam, SWA. [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 99.546 42.273 57.273 28.442 28.442 4.442 46.715 0 100% 47%
May - 2021
03- Packages Work in progress.
No Image
Package 1
Package 2
Package 3
969
(OG)
191573-150009 - Construction of Boys Degree College, Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 178.499 126.041 18.818 11.417 11.417 8.416 134.457 33.64 81% 75%
May - 2021
01- Unit MB F/F roof ceiling in progress. Type-III roofing in progress. Type-IV Qtr: roofing in progress. Cafeteria roofing in progress.
No Image
Construction of Boys Degree College, Orakzai
970
(OG)
191579-160460 - Establishment of GGDC Bara, Khyber Agency. (G.D) [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 169.443 56.334 100.386 61.561 61.561 36.912 93.246 12.723 92% 55%
May - 2021
Work in progress, 33% work completed. Demand Rs: 12.82 M
No Image
GGDC Bara, Khyber Agency. (G.D) [MA]