Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
782 (New) |
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 526.033 | 0 | 50 | 95 | 95 | 30 | 30 | 476.033 | 10% |
6% May - 2021 |
Layout given |
No Image |
Upgradation of RHC Chuprial into Category-D Hospital Swat | |||||||||||||||||||
783 (New) |
200196-Up-gradation of SINOR, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 491 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Revenue componenet only |
No Image |
784 (New) |
200204-F/S for Upgradation of Civil Hospital Madyan to Category C District Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 200 | 200 | 0 | 0 | 0 | 0 |
May - 2021 |
PC-II submitted |
No Image | |
785 (New) |
200213-F/S for upgradation of Kalam Hospital Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II submitted to Client Deptt |
No Image |
786 (New) |
200199-F/S for Upgradation of DHQ Hospital Haripur in to Cat-A Hospital, Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II submitted |
No Image |
787 (New) |
180582-Safe Disposal of Hospital infectious Waste in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
788 (New) |
190527-Upgradation of RHC Jolagram-Malakand and RHC Jowar-Buner to Cat-D Hospitals in Malakand Division. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
NESPAK Conusltant hired design & estimation in progress |
No Image |
788 (New) |
190527-Upgradation of RHC Jolagram-Malakand and RHC Jowar-Buner to Cat-D Hospitals in Malakand Division. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Malakand component deleted by Health Deptt: |
No Image |
788 (New) |
190527-Upgradation of RHC Jolagram-Malakand and RHC Jowar-Buner to Cat-D Hospitals in Malakand Division. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 560 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
789 (New) |
200049-Revamping of Non-Teaching DHQs across KP. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3361.063 | 0 | 500 | 500 | 0 | 0 | 0 | 2861.063 | 15% |
- May - 2021 |
Approved. |
No Image |
790 (New) |
200240-F/S for Provision of significant diagnostic facilities i.e. CT Scan, MRI etc in DHQ Hospitals of District Upper and Lower Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
791 (OG) |
60046-Construction of Building for Gomal Medical College, D.I Khan, Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2531.513 | 114.319 | 74.319 | 74.319 | 45.818 | 2577.331 | 0 | 100% |
100% May - 2021 |
Pack-1 & 2 - Completed.
Pack-3 & 4 - Completed & H/O
Rs: 40 M surrendered surplus to requriement |
No Image |
Scope of work:
Package-I
Package-II
| |||||||||||||||||||
792 (OG) |
180468-Establishment of Paramedics College & Male Nursing College in Lakki Marwat (PC-II approved by PDWP on 08-10-2019) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2265.73 | 127.108 | 150 | 0 | 0 | 0 | 127.108 | 1988.622 | 12% |
6% May - 2021 |
Tender will be floated shortly |
No Image |
792 (OG) |
180468-Establishment of Paramedics College & Male Nursing College in Lakki Marwat (PC-II approved by PDWP on 08-10-2019) |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 185.586 | 127.108 | 150 | 0 | 0 | 0 | 127.108 | 0 | 100% |
68% May - 2021 |
01- Unit
PC-II approved
Cost of Land Payed to DC for Rs. 127.039 (M)
PDWP to be helld on 22/12/20. |
No Image |
Paramedics College & Male Nursing College in Lakki Marwat | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 810.014 | 80 | 70 | 70 | 60 | 870.014 | 27.303 | 97% |
95% May - 2021 |
01-Unit
1. Academic/admin block, cafetaria, library, mosque In progress.
2. Admin Block-I Completed, Block-II & III 75 % |
No Image |
Scope of work:
Package-I
Package-II
| |||||||||||||||||||
794 (OG) |
130618-Establishment of Kohat Institute of Medical Sciences (KIMS) |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2197 | 1351.762 | 200 | 200 | 200 | 199.999 | 1551.761 | 645.238 | 71% |
71% May - 2021 |
03- Packages
Pac - 1:
Basement, G+3 Strcutre competed, G/Floor 50%, BB Work Completed & Flooring 60% Completed, F/F 50%, BB work Completed & Flooring 60% Completed
2nd Floor: 50% BB work completed & Flooring 60% completed
3rd Floor BB work completed & Flooring 60% Completed
Pac - 2 :
Basement Slab Completed, P. Beam Completed, G.F Roof Slab laid, BB Work & Flooring Completed
1st Floor Laid BB & Flooring Completed
2nd Floor BB work & Flooring Completed
3rd Floor Completed
4th Floor BB work completed
Pac - 3 :
C/Wall 90% Completed
Girls Hostel G+5 roof slab completed and BB work is 100% completed, Flooring Completed watch Tower 2/4 Completed drain completed
Common Facility Block: G/F Plaster in Progress, F/F BB work in progress, 2nd Floor roof laid, 3rd floor roof laid
4th Floor steel work in progress |
No Image |
1) Pack-1 - Medical Block ( B + G + 4 Stoarey )
2) Pack-2 - Dental Block & Hospital ( B + G + 4 Stoarey )
3) Pack-3 - Dev Work + Girls Hostel ( B + G + 4 Stoarey ) ( B + G + 4 Stoarey )
4) Pack 4 - Common Facility Centre | |||||||||||||||||||
795 (OG) |
130289-Construction of 02 Lecture Theaters, Auditorium, Building for Prosthodontics, Tube Well & Overhead Tank in Khyber College of Dentistry, Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 580.434 | 361.926 | 40 | 123 | 123 | 123 | 484.926 | 178.508 | 69% |
84% May - 2021 |
Girls Hostel completed
Block A & B Completed
Tube well over head tank completed
VRF const: work started
Demand Rs: ? |
No Image |
Scope of work:
| |||||||||||||||||||
796 (OG) |
130619-Establishment of KMU Institute of Nursing & Medical Technology, Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 877.922 | 0 | 114.73 | 16.588 | 16.588 | 16.588 | 0 | 0 |
May - 2021 |
Package-1, 2 & 3 PC-IV sent for handing/taking of building
Cannot be completed due to for non energaization of institute by WAPDA |
No Image | |
Scope of work:
| |||||||||||||||||||
797 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I) |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2569.253 | 1301.986 | 100 | 578.189 | 578.189 | 96.4 | 1398.386 | 1167.267 | 55% |
54% May - 2021 |
01- Unit
Main building (3 blocks) - Structure work completed Flooring in progress. U/G &O/H tank completed.
Summary submitted fro Enhancement.
(Executed by FWO) |
No Image |
Establishment of Nowshera Medical College (Phase-I)
Scope of work:
| |||||||||||||||||||
798 (OG) |
180164-Construction of Hostel for Nowshera Medical College. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 644 | 0 | 36.662 | 36.662 | 36.662 | 36.466 | 36.466 | 607.338 | 6% |
6% May - 2021 |
01- Unit
Lalazar Consultants of the project.
Work order issued. |
No Image |
-Construction of Hostel for Nowshera Medical College. | |||||||||||||||||||
799 (OG) |
160443-Construction of Purpose Built Building for Gajju Khan Medical College Swabi (PC-II approved by PDWP on 18-02-2020). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1500 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
May - 2021 |
Land paymnet made to DC Swabi Rs.170 M
PC-I under preppartion by the Consultants |
No Image | |
Construction of Purpose Built Building for Gajju Khan Medical College Swabi | |||||||||||||||||||
800 (OG) |
90334-Establishment of Bacha Khan Medical College, Mardan. (Phase-II) |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1765.493 | 1162.393 | 195 | 229.471 | 229.471 | 149.482 | 1311.875 | 408.1 | 77% |
74% May - 2021 |
01- Unit
Academic/admin block, auditorium, girls hostel,Guest House, joinery, finishing in progress.
Over head tank, BW,Sewerage Line, Road work completed. Land scope, Lift work, not yet started Aircondition work Work order issued. |
No Image |
PK-24, Mardan
Scope of work:
| |||||||||||||||||||
801 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters, Laboratories and Auditorium at Saidu Medical College and Staff Hostels at Saidu Group of Teaching Hospitals, Swat |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1100 | 379.978 | 200 | 200 | 200 | 127.5 | 507.478 | 520.022 | 53% |
46% May - 2021 |
Original Scope- Completed.
Revised scope - Work started . |
No Image |
Civil Work
WAPDA payment | |||||||||||||||||||
802 (OG) |
190460-Establishment of Saidu College of Dentistry in the existing Saidu Medical College (PC-II approved on 08-10-2019) |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 708.328 | 0 | 100 | 195 | 195 | 86.315 | 86.315 | 608.328 | 14% |
12% May - 2021 |
Raft foundation completed
R/Wall and basement column in progress |
No Image |
803 (OG) |
190529-Purchase of Equipment/other requirements for Dental College/Dental Departments in Saidu Group of Teaching Hospital, Swat |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 388.315 | 55 | 0 | 0 | 0 | 0 | 55 | 0 | - |
- May - 2021 |
No Image | |
804 (OG) |
150521-Establishment of Timergara Medical College Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 56.321 | 50 | 35 | 35 | 4.398 | 60.719 | 0 | 100% |
61% May - 2021 |
01- Unit
Main Building finishing in progress.
Demand Rs: 10-00 M |
No Image |
Dir Lower | |||||||||||||||||||
805 (New) |
190067-Establishment of Charsadda Medical College, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1300 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II submitted Aug 2021
to health. Pre PDWP held. |
No Image |
Medical College Dist: charssadda | |||||||||||||||||||
806 (New) |
200050-Upgradation of existing 09 Nursing Schools of Province to Nursing Colleges (HMC, LRH, KTH Peshawar, Kohat, Bannu, D.I.Khan, Mardan, Swat & Abbottabad) (Phase-I & II). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 109.825 | 0 | 0 | 0 | 0 | 0 | 0 | 109.825 | - |
- May - 2021 |
Tendering floated on 24-05-21. Tech: evalation under process |
No Image |
806 (New) |
200050-Upgradation of existing 09 Nursing Schools of Province to Nursing Colleges (HMC, LRH, KTH Peshawar, Kohat, Bannu, D.I.Khan, Mardan, Swat & Abbottabad) (Phase-I & II). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 99 | 0 | 0 | 0 | 0 | 0 | 0 | 99 | - |
- May - 2021 |
scheme approved in pre PWFD 26-01-21
Tender under prcress |
No Image |
806 (New) |
200050-Upgradation of existing 09 Nursing Schools of Province to Nursing Colleges (HMC, LRH, KTH Peshawar, Kohat, Bannu, D.I.Khan, Mardan, Swat & Abbottabad) (Phase-I & II). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 286.286 | 0 | 0 | 0 | 0 | 0 | 0 | 286.286 | - |
- May - 2021 |
Site not handed over to C&W Department. |
No Image |
806 (New) |
200050-Upgradation of existing 09 Nursing Schools of Province to Nursing Colleges (HMC, LRH, KTH Peshawar, Kohat, Bannu, D.I.Khan, Mardan, Swat & Abbottabad) (Phase-I & II). |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 134.695 | 0 | 0 | 0 | 0 | 0 | 0 | 134.695 | - |
- May - 2021 |
Tendering in process. |
No Image |
806 (New) |
200050-Upgradation of existing 09 Nursing Schools of Province to Nursing Colleges (HMC, LRH, KTH Peshawar, Kohat, Bannu, D.I.Khan, Mardan, Swat & Abbottabad) (Phase-I & II). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 49.13 | 0 | 0 | 0 | 0 | 0 | 0 | 49.13 | - |
- May - 2021 |
Tender under prcress |
No Image |
807 (OG) |
120888-Integration of Health Services Delivery with special focus on MNCH, LHW, EPI and Nutrition Programme (DFID & AusAid Assisted. Foreign Cost Rs. 8.12 Bn). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.328 | 9.916 | 0 | 0 | 0 | 0 | 9.916 | 1.412 | - |
88% May - 2021 |
05/05 units work Completed. |
No Image |
1. BHU Marai Payan ? Rs. 1.170 M, TS 1.051
2. BHU Khadar Khel ? Rs. 1.933 M, TS 1.873
3. RHC Gumbat ? Rs. 2.561 M
4. RHC Chorlaki? Rs. 4.720 M
5. BHU Tolanj.? Rs. 0.944 M | |||||||||||||||||||
807 (OG) |
120888-Integration of Health Services Delivery with special focus on MNCH, LHW, EPI and Nutrition Programme (DFID & AusAid Assisted. Foreign Cost Rs. 8.12 Bn). |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.45 | 9.689 | 0 | 0 | 0 | 0 | 9.689 | 0.761 | - |
93% May - 2021 |
07- Units
All Completed & HO. |
No Image |
| |||||||||||||||||||
807 (OG) |
120888-Integration of Health Services Delivery with special focus on MNCH, LHW, EPI and Nutrition Programme (DFID & AusAid Assisted. Foreign Cost Rs. 8.12 Bn). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5806.63 | 3130.812 | 0 | 0 | 0 | 0 | 3130.812 | 0 | - |
- May - 2021 |
No Image | |
808 (OG) |
130218-Integrated Vector Control Programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 442.177 | 175.436 | 0 | 0 | 0 | 0 | 175.436 | 0 | - |
- May - 2021 |
No Image | |
809 (OG) |
140771-Strengthening of TB Control Programme in Khyber Pakhtunkhwa (Phase-II). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.837 | 111.918 | 0 | 0 | 0 | 0 | 111.918 | 0 | - |
- May - 2021 |
No Image | |
810 (OG) |
140772-Treatment of Poor Cancer Patients (Phase-II). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4942.861 | 2767.212 | 0 | 0 | 0 | 0 | 2767.212 | 0 | - |
- May - 2021 |
No Image | |
811 (OG) |
150526-Integrated HIV, Hepatitis and Thalassemia Control Program |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 41.994 | 0 | 0 | 0 | 0 | 41.994 | 0 | - |
- May - 2021 |
No Image | |
812 (OG) |
160239-Establishment of Safe Blood Transfusion Project (Phase-II) (German Grant) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 477.472 | 191.096 | 0 | 0 | 0 | 0 | 191.096 | 0 | - |
- May - 2021 |
No Image | |
813 (OG) |
170592-Integrated Disease Surveillance Response System (IDRS) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 395.149 | 24.242 | 0 | 0 | 0 | 0 | 24.242 | 0 | - |
- May - 2021 |
No Image | |
814 (OG) |
170593-Extension of D-Talk and Insulin for Life |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 234.55 | 91.235 | 0 | 0 | 0 | 0 | 91.235 | 0 | - |
- May - 2021 |
No Image | |
815 (New) |
190404-Provision of Life-Saving Maternal and Reproductive Health, Protection Support Services for Women and Girls in Khyber Pakhtunkhwa through UNFPA (AusAid Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.003 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
816 (New) |
200037-Integration of Health Services Delivery with special focus on MNCH, LHW and Nutrition Programme. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
817 (New) |
200046-Topping up of preventive Healthcare regime (Hepatitis, TB, EPI, NCD, HIV etc.). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 96.2 | 96.2 | 89.699 | 1843.453 | 482.449 | 80% |
76% May - 2021 |
01-Unit
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3
| |||||||||||||||||||
819 (OG) |
130630-Upgradation of Existing Accident & Emergency Unit and ICU at HMC, Peshawar. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1205 | 0 | 698 | 140 | 140 | 110.458 | 110.458 | 507 | 58% |
9% May - 2021 |
Tyles work in progress. Plumbing work in progrss.
Electrict work in progress.
Revised TS Submitted to SE |
No Image |
HMC Peshawar
Scope of work:
| |||||||||||||||||||
820 (OG) |
170536-Establishment of Orthopedic & Spine Surgery Block at Hayat Abad Medical Complex (HMC), Peshawar |
Peshawar MPD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 445.158 | 240.156 | 133 | 120 | 120 | 119.204 | 359.36 | 72.002 | 84% |
81% May - 2021 |
5 Storey- Semi Basemnet, Ground, G+4 car parking, U/G W.Tank & OHT, finishign in progress.
TS Submitted |
No Image |
Establishment of Orthopedic & Spine Surgery Block at Hayat Abad Medical Complex (HMC), Peshawar | |||||||||||||||||||
821 (OG) |
180336-Additional Works in Peshawar Institute of Cardiology |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 383.956 | 321.76 | 134.389 | 60.628 | 60.628 | 60.628 | 382.388 | 0 | 100% |
100% May - 2021 |
Original work 90% completed.
Lifts , Autio door, generators etc installed
Cannot be completed due to revised scope of work awatied upon the request of Hospital Director. |
No Image |
Scope of work:
| |||||||||||||||||||
822 (OG) |
130589-Upgradation of Bacha Khan Medical Complex for Teaching Purpose of Gajju Khan Medical College, District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1389.13 | 1020.214 | 0.001 | 10 | 10 | 4.03 | 1024.244 | 368.915 | 73% |
74% May - 2021 |
01- Unit
PC-II Rs: 25 M
dated: 28-039-13
PIT inquiry in progress
1. Paramedics block (3-Nos) G+3 = Structure work completed.
2. Specialist Flats (03-Nos) G+2
3. Nurse flats (03-Nos) G+2
4. OPD Block (01-No) Completed
5. Burn Block (01-No) Marble Flooring in progress.
Re-tendering of HVAC, Lifts etc on progress. (revised Scope) |
No Image |
Upgradation of Bacha Khan Medical Complex for Teaching Purpose of Gajju Khan Medical College, District Swabi. | |||||||||||||||||||