Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.771 | 36.807 | 75.424 | 75.424 | 75.424 | 32.417 | 69.224 | 0 | 100% |
81% May - 2021 |
07- Units
1 G/F roof laid
2 Finishing
3 G/F 1st floor roof laid
4 Tender called
5 Tender cancelled
6 1st floor roof laid
7 finishing stage |
No Image |
1) GGPS Khwajamad Landidak PK-72.?.?.?.. (TS 17.650)
2 GPS Farman Manzaga ?.?.?.. (TS 17.812)
3 GGPS Naqib Ullah ?.?.?.. (TS 17.00)
4 GGPS Tehsin Kot
5 GPS Mir Abbas Khan
6 GGPS Ghazi Baka ?.?.?.. (TS 18.56)
7 GGPS Jangi Killa Pirba Khel | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
AA awaited. |
No Image |
1. GPS No.2 Charsadda PK-59? Rs: 18.926 M
2. GPS Matta Pk-60? Rs: 18.876 M
| |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.521 | 1.098 | 47.207 | 47.207 | 47.207 | 33.41 | 34.508 | 9.216 | 84% |
60% May - 2021 |
04- Units
1. Finishing in progress
2. Dev: work completed
3. The old building not yet dismantled
4. Excvation as in progress |
No Image |
1. GPS Dehrai Talash
2. GPS Likor
3. GPS Beshingram
4. GPS Asbanr | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 9.256 | 29.877 | 29.877 | 29.877 | 11.34 | 20.596 | 23.242 | 63% |
33% May - 2021 |
3- Units
1 work order issued
2 G/F in progress |
No Image |
1) GPS Nasrat PK-91
2) GPS Atir | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I/DCE for Rs.22.256 m submitted to DEO Male Han |
No Image |
Reconstruction of GPS No.1 Azimi Banda Hangu | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.378 | 4.5 | 57.384 | 57.384 | 57.384 | 19.954 | 24.454 | 19.494 | 76% |
30% May - 2021 |
6 Units
1 Work in progress
5 procurement in prosces. |
No Image |
GGPS koka Pk 40 | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I/DCE submitted to DEO on 04/04/2019. |
No Image |
1) GPS Kohi Maidan | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.785 | 0 | 38.419 | 38.419 | 38.419 | 38.419 | 38.419 | 23.366 | 62% |
62% May - 2021 |
03- Units
1. Dismentling in progress
2. Work order issued on 11-2020
3. Dismentling in progress |
No Image |
1) GPS Sangerh PK-82 .?. Rs. 20.595 M
2) GPS City Centre PK-82 .?. Rs. 20.595 M
3) GPS Jangle Khel PK-82 .?. Rs. 20.595 M
| |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30.759 | 16.093 | 9.565 | 9.565 | 9.565 | 8.224 | 24.317 | 5.101 | 83% |
79% May - 2021 |
03- Units
1. Completed & H/O
2. Completed & H/O
3. Not yet started as the old rooms are to be demolished which are awaited on the part of Education Dept. |
No Image |
1) GPS Nar Asparli PK-74/93 .?.. Rs; 19.300 M (TS 18.369)
2) GPS Faqir Karhi Allah Yar .?.. Rs; 5.448 M (TS 5.996)
3. GPS tabbi Murad No. 1.?.. Rs; 6.011 M | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.3 | 16.093 | 8.565 | 8.565 | 8.565 | 6.943 | 23.036 | 0 | 100% |
100% May - 2021 |
3- units
1- B/Wall 95% completed.
MB Marble flooring in progress. Lavatory & Pressure pump completed.
2- Physicall completed.
3- Not yet started as the old rooms are to be demolished. |
No Image |
1) GPS Nar Asparli PK-74/93 .?.. Rs; 19.300 M (TS 18.369 )
2) GPS Faqir Karhi Allah Yar .?.. Rs; 5.448 M (TS 5.996)
3. GPS tabbi Murad No. 1.?.. Rs; 6.011 M | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I/DCE for Rs.18.960 m, Rs.18.897 m and Rs.18.85 |
No Image |
1) GPS Sohai Bandi UC Lassan Nawab PK-32 | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.607 | 6.235 | 44.25 | 44.25 | 44.25 | 13.601 | 19.836 | 0 | 100% |
100% May - 2021 |
06- Units
1. M/B Finihsing Stage, B/W in progress
2. AA. Awaied
3. AA. Awaied
4. AA. Awaied
5. Main Building F/F in progress
6. AA. Awaied |
No Image |
1) GGPS Gujar Garhi PK-54 ? Rs: 19.607.?. (TS 18.667)
2) GGPS Gujar Garhi
3. GPS Machi
4. GGPS Par Hoti No. 2
5. GPS Sowaryan ? Rs: 21.523 M
6. GGPS Karwan
| |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.096 | 70.952 | 11.314 | 11.314 | 11.314 | 6.509 | 77.461 | 0 | 100% |
96% May - 2021 |
05- Units
1. Completed
2. Completed
3. FF + 2nd Floor Finishing
4. Finishing
5. Plastering in progress |
No Image |
1. GGPS Taru Jabba ? Rs: 16.969 M
2. GGPS Banda Sheikh? Rs: 21.406 M
3. GGPS No.1 Dagi Qadeem ? Rs: 22.723 M
4. GGPS No.1 Manki Shairf ? Rs: 19.998 M
5. GGPS Ghari Moim? Rs: 22.452 M | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.727 | 4.785 | 24.086 | 24.086 | 24.086 | 17.554 | 22.339 | 4.856 | 86% |
66% May - 2021 |
02- Units
1. Super Structure completed, B/W completed, Bore Completed, G/F roof laid, G/F Slable in progress
2. M/B Raft completed, B/B work/RCC column in progress |
No Image |
1. GGPS Hamid Abad (Pk-66)? Rs: 16.104 M, TS 14.977
2. GPS No.2 Mera Urmar Payan? Rs: 17.623 M, TS 16.748 | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 852.811 | 373.303 | 479.508 | 479.508 | 0 | 0 | 373.303 | 0 | - |
- May - 2021 |
No Image | |
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.184 | 60.983 | 41.02 | 41.02 | 41.02 | 31.05 | 92.033 | 0 | 100% |
100% May - 2021 |
07- Units
1. Completed PC-IV Submitted
2. 04 C/room DPC Level (Revised Balance work)
3. Completed & H/O
4. Finihsing in progress
5. 1st Floor Laid roof level
6. Roof level
7. Completed & H/O |
No Image |
1) GPS Mughai Kot PK-31 .?. Rs: 19.00 M (TS 19.940)
2) GPS Spinkani (Pk-47) .?. Rs: 15.00 M (TS 16.451)
3) GPS Tarkha Dobian (Pk-46) .?. Rs: 9.094 M (TS 9.6)
4) GPS Ayub Khan Killi Pk-46 .?. Rs: 14.300 M (TS 14.258)
5) GPS Ghar Aka Khel Pk-47 .?. Rs: 12.700 M (TS 12.620)
6) GPS No2 Jalsai Pk-46 .?. Rs: 12.700 M
7) GPS Adina Khud Pk-46 .?. Rs: 9.241 M (TS 9.067) | |||||||||||||||||||
393 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa (less 47 units). |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 101.13 | 28.907 | 69.413 | 69.413 | 69.413 | 29.341 | 58.248 | 2.81 | 97% |
58% May - 2021 |
06 - Units
01 unit- H/O
05 units- in porgress
1. F/F in progress
2. Roofing in progress
3. F/F roof laid
4. Completed & H/O
5. Work in foundation
6. F/F roof laid |
No Image |
1. GGPS Fazal Baig Garrai .?. Rs: 16.855 M (TS 12.817)
2. GGPS Bajawa .?. Rs: 16.855 M
3. GPS Baidara No.1 .?. Rs: 16.855 M (TS 13.49)
4. GPS Bodigaram .?. Rs: 16.855 M (TS 13.22)
5. GPS Bakoor .?. Rs: 16.855 M
6. GGPS Aboha .?. Rs: 16.855 M | |||||||||||||||||||
394 (OG) |
180501-Development of Play Areas in Primary Schools of Khyber Pakhtunkhwa. (SBSE) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
395 (OG) |
190406-Capacitating 500 ECE Rooms in Government Primary Schools in Khyber Pakhtunkhwa (SBSE) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
396 (OG) |
200166-Refugees & Host Communities under IDA-18-Regional Sub Window SH: Khyber Pakhtunkhwa Human Capital Investment Project (KPHCIP) Education Component |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
397 (New) |
200025-Establishment of 100 Primary Schools in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.213 | 0 | 0 | 0 | 0 | 0 | 0 | 40.213 | - |
- May - 2021 |
Approved. |
No Image |
GPS Shah Khel Pate Khanorai | |||||||||||||||||||
397 (New) |
200025-Establishment of 100 Primary Schools in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I has been submitted on 28-10-2020 |
No Image |
GGPS at Bilal Abad U/C Behram Dheri | |||||||||||||||||||
397 (New) |
200025-Establishment of 100 Primary Schools in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2000 | 0 | 480 | 480 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
397 (New) |
200025-Establishment of 100 Primary Schools in Khyber Pakhtunkhwa |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.981 | 0 | 0 | 0 | 0 | 0 | 0 | 57.981 | - |
- May - 2021 |
Approved |
No Image |
GGPS at Bilal Abad U/C Behram Dheri | |||||||||||||||||||
397 (New) |
200025-Establishment of 100 Primary Schools in Khyber Pakhtunkhwa |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.298 | 0 | 0 | 0 | 0 | 0 | 0 | 20.298 | - |
- May - 2021 |
Approved |
No Image |
398 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 705.906 | 172.385 | 169.667 | 169.667 | 146.832 | 852.738 | 0 | 100% |
100% May - 2021 |
01- Unit
Admin Block & Library flooring in progrees.
Academic Block,Student hostel: plastering & flooring in progress.
Guest House: plaster in progress.
House Master : Flooring in progress.
Mess Hall : plaster in progress.
Road: WB in progress.
OHR T/W completed.
BW: East sote Southern side completed.
Cat-III: block ground floor Ist & 2nd slabe completed. BB work in progeres. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
399 (OG) |
190505-Upgradation of GHS Kutar Pan to GHSS level Distt Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.7 | 0 | 42.726 | 56.055 | 56.055 | 27.811 | 27.811 | 0 | 100% |
65% May - 2021 |
01- Unit
Finishing in progress |
No Image |
400 (OG) |
190506-Upgradation of Govt Girls Middle School Mugahlki , Mia Essa to GGHS level Distt Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.911 | 0 | 82.99 | 98.52 | 98.52 | 45.191 | 45.191 | 0 | 100% |
55% May - 2021 |
02- Units
1. GF Roof laid
2. 1st Floor roofing in progress, Finishing in progress |
No Image |
401 (OG) |
160525-Establishment of Girls Cadet College at Mardan. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2395.677 | 608.21 | 500 | 500 | 500 | 286.55 | 894.76 | 1287.467 | 46% |
37% May - 2021 |
4 Packages -
Work in progress on all packages.
Orally communicated for Rs: 120 surrendered on 28-05-2021 |
No Image |
Girls Cadet College at Mardan
04 Nos Packages | |||||||||||||||||||
402 (OG) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.712 | 21.73 | 81.712 | 77.184 | 77.184 | 25.701 | 47.431 | 0 | 100% |
51% May - 2021 |
01-Unit
2nd Floor roof in porgress
B/Wall 70% completed
over head water tank 80% completed |
No Image |
Buner | |||||||||||||||||||
403 (OG) |
160524-Establishment of Cadet College Swat (Phase-III) |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1348 | 400 | 0 | 0 | 0 | 0 | 400 | 0 | - |
- May - 2021 |
Executed by Pak Army |
No Image |
Cadet College Swat | |||||||||||||||||||
404 (OG) |
180503-Development of Barikot Center/Site for Scout Purpose |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45.062 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I submitted to Edu on MRS-2020. |
No Image |
405 (OG) |
70613-Establishment of Dir Model School at Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.806 | 93.076 | 93 | 3.51 | 3.51 | 0 | 93.076 | 0 | 100% |
63% May - 2021 |
Completed |
No Image |
PK-91, Upper Dir | |||||||||||||||||||
406 (OG) |
200023-Construction of Internal Road and a New Bus for Abbottabad Public School (Non-ADP) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.05 | 0 | 22.049 | 22.049 | 22.049 | 8.119 | 8.119 | 0.001 | 100% |
37% May - 2021 |
01- Unit
Work being started |
No Image |
406 (OG) |
200023-Construction of Internal Road and a New Bus for Abbottabad Public School (Non-ADP) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
406 (OG) |
200023-Construction of Internal Road and a New Bus for Abbottabad Public School (Non-ADP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.05 | 13 | 22.05 | 22.05 | 0 | 0 | 13 | 0 | - |
- May - 2021 |
No Image | |
407 (OG) |
150711-Remodelling, Redesigning and Rehabilitation of Pilot High School for Girls in Haripur City. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 175.5 | 115.473 | 69.987 | 69.987 | 69.987 | 21.34 | 136.813 | 0 | 100% |
78% May - 2021 |
Finishing in progress. |
No Image |
Haripur City | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.387 | 118.739 | 38.096 | 38.096 | 38.096 | 3.352 | 122.091 | 27.552 | 85% |
66% May - 2021 |
01- Unit
Main building - roof laid. BW 90% completed.,,,,
An amount of Rs.0.266 m to Pesco Batagram for HT line shifting. |
No Image |
Construction of Model School at Moza Chapperg | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.598 | 36.127 | 60 | 60 | 60 | 28.957 | 65.084 | 101.471 | 49% |
33% May - 2021 |
01- Unit
Excavation in progress, B/Wall 70% completed, Layout given
Cannot be completed due to revision involoved
Rs: 22.000 M surrender |
No Image |
Bacha Khan Model School Charsadda | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.99 | 30.125 | 15.823 | 15.823 | 15.823 | 4.305 | 34.43 | 0 | 100% |
88% May - 2021 |
01- Unit
Finishing in progress |
No Image |
GHS Bumborate | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125.915 | 46.749 | 4.274 | 4.274 | 4.274 | 1.965 | 48.714 | 74.892 | 41% |
39% May - 2021 |
01- Unit
B/wall 2200 ft completed
Class room 10 Nos finishing in progrss
Canot be completed due to revision of scheme |
No Image |
Establishment of Model School Hangu | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 246.853 | 169.674 | 58.809 | 58.809 | 58.809 | 54.699 | 224.373 | 18.37 | 93% |
91% May - 2021 |
Consultant selected.
2 Components.
MB finishing in progress.
Multi purpose Hall finishing in progress. |
No Image |
Establishment of Model School Haripur (215.623 15 | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.217 | 139.036 | 31.837 | 31.837 | 31.837 | 31.83 | 170.866 | 28.344 | 86% |
86% May - 2021 |
Finsihing Stage
B/W in progress
Demand Rs: 30 M |
No Image |
Model School Karak | |||||||||||||||||||
408 (OG) |
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 691.2 | 583.276 | 16.724 | 16.724 | 0 | 0 | 583.276 | 91.2 | 87% |
84% May - 2021 |
No Image | |
409 (OG) |
140197-Upgradation of 100 Govt : High Schools to Higher Secondary level in Khyber Pakhtunkhwa (B&G 30:70) on need basis (less 05 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 202.969 | 130.696 | 59.799 | 59.799 | 59.799 | 26.447 | 157.143 | 12.474 | 94% |
77% May - 2021 |
09- Units
1. Completed
2. Completed & H/O
3. M/B G/Floor, 1st floor marble in progress
4. Completed
5. Completed & H/O
6. 1st floor roof beam laid
7. Builidng completed Toilet block roofing in progress
8. Completed & H/O
9. Dev: work in progrss, M/B S/Structure in progress |
No Image |
1) GHS Mohri Bed Bhen PK-47 .?. Rs: 23.484 M .?.?.?. TS 20.02
2) GPS Mohri Bed Bhen .?. Rs: 20.277 M .?.?.?. TS 24.152
3. GGHS Malach .?. Rs: 20.277 M
4. GHS Seer Sharquir (CM Directive) .?. Rs: 20.765 M .?.?.?. TS 21.946
5. GHS Kokal Barseen .?. Rs: 20.76 M .?.?.?. TS 18.335
6. GHS Pind Kargu Khan .?. Rs: 20.76 M
7. GHS NO. 3 Abbottabad .?. Rs: 24.849 M .?.?.?. TS 22.02
8. GHS Chando Maira S/T GHS Bodla .?. Rs: 24.849 M .?.?.?. TS 23.152
9. GHS Lakhala .?. Rs: 24.258 M | |||||||||||||||||||
409 (OG) |
140197-Upgradation of 100 Govt : High Schools to Higher Secondary level in Khyber Pakhtunkhwa (B&G 30:70) on need basis (less 05 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40 | 30.449 | 17.665 | 17.665 | 17.665 | 16.509 | 46.958 | 0 | 100% |
100% May - 2021 |
02- Units
1. M/B Roof liad
2. Completed |
No Image |
1) GHS Ghora Baka Khel PK-72 S/T Mammand Khel
2) GGHS Mumbati Barakzai .?.?.?.. (TS 21.299) | |||||||||||||||||||
409 (OG) |
140197-Upgradation of 100 Govt : High Schools to Higher Secondary level in Khyber Pakhtunkhwa (B&G 30:70) on need basis (less 05 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.106 | 43.5 | 3.325 | 3.325 | 3.325 | 2.105 | 45.605 | 0.281 | 99% |
97% May - 2021 |
02- Units
1. Completed
2. Completed & H/O |
No Image |
1) GHS Tangora PK-78 ? Rs: 23.553 M
2) GHS Kulyarai ? Rs: 23.553 M | |||||||||||||||||||
409 (OG) |
140197-Upgradation of 100 Govt : High Schools to Higher Secondary level in Khyber Pakhtunkhwa (B&G 30:70) on need basis (less 05 units). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 52.147 | 44.21 | 6.752 | 6.752 | 6.752 | 2.412 | 46.622 | 1.185 | 98% |
89% May - 2021 |
02- Units
1. Completed & H/O,
2. Finishing in progress. |
No Image |
1. GHS Rahmat Ullah Khan Koroona PK-60? RS: 25.530 M
2. GHS Dalazak S/T Subkhan Khwar PK-60? RS: 27.067 M | |||||||||||||||||||
409 (OG) |
140197-Upgradation of 100 Govt : High Schools to Higher Secondary level in Khyber Pakhtunkhwa (B&G 30:70) on need basis (less 05 units). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.99 | 30.125 | 6.094 | 6.094 | 6.094 | 1.453 | 31.578 | 2.771 | 93% |
81% May - 2021 |
M/F roof in progress. B/Wall work in progress. |
No Image |
GHS Bumborate | |||||||||||||||||||